PMP Exam Topic 36 Question 357 Discussion:
Question #: 357
Topic #: 36

A project team completed sprint planning, but at the end of the session the project lead receives a message from a stakeholder about a legislative change that requires a new validation rule in one backlog item committed for the sprint. What should the project lead do?


A.

Remove the current backlog item from the sprint and replace it with defect fixing


B.

Remove the current backlog item from the sprint and replace it with a similar item


C.

Update the backlog and advise the team to add this to the acceptance criteria


D.

Update the product backlog and include the change as a high priority for the next iteration