PMI Project Management Professional (PMBOK 7th Version) PMP Question # 635 Topic 64 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 635 Topic 64 Discussion

PMP Exam Topic 64 Question 635 Discussion:
Question #: 635
Topic #: 64

Three months after creating a project schedule, the scope of a project significantly changed, resulting in a schedule rebaselining. One month after rebaselining, the project is two weeks behind schedule with a cost performance index (CPI) of 0.93. What should the project manager do to help get the project back on schedule?


A.

Crash the project with two additional contract resources for the newly identified tasks.


B.

Meet with the project stakeholders and inform them that the project is going to be delayed.


C.

Manage the schedule’s critical path, as this was an approved scheduling change.


D.

Review the project schedule and find ways to fast-track the overall project schedule.