Three months after creating a project schedule, the scope of a project significantly changed, resulting in a schedule rebaselining. One month after rebaselining, the project is two weeks behind schedule with a cost performance index (CPI) of 0.93. What should the project manager do to help get the project back on schedule?
Submit