PMI Project Management Professional (2025 Version) PMP Question # 358 Topic 36 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 358 Topic 36 Discussion

PMP Exam Topic 36 Question 358 Discussion:
Question #: 358
Topic #: 36

A company is launching a new product that has to be ready before the summer season begins. After the discovery process, the team realizes that the requirements are very uncertain.

What should the project manager do?


A.

Invite stakeholders to discuss project requirements prioritization.


B.

Register a risk and define a contingency plan to finish the project on time.


C.

Ask to include some business subject matter experts (SMEs) in the team.


D.

Assist the team in proposing a minimum viable product (MVP).


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.