Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 359 Topic 36 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 359 Topic 36 Discussion

PMP Exam Topic 36 Question 359 Discussion:
Question #: 359
Topic #: 36

After finishing the planning session for a new project, the team agrees that the project duration needs to be 12 months. However, the project sponsor asks to release the product before the end of the project. What should the project manager do first?


A.

Update the risk register and escalate it to the sponsor


B.

Assist the team in proposing a minimum viable product (MVP)


C.

Request the stakeholders to reduce the project backlog to finish on time


D.

Ask to increase the capacity of the team to deliver the project on time


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.