New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 361 Topic 37 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 361 Topic 37 Discussion

PMP Exam Topic 37 Question 361 Discussion:
Question #: 361
Topic #: 37

The project manager is having difficulty obtaining approval of the project requirements because there is disagreement among the project stakeholders This issue is putting the project schedule at risk

What should the project manager do first to facilitate the approval of project requirements'?


A.

Review the project charter


B.

Perform a stakeholder analysis


C.

Identify the source of the disagreement


D.

Hold a team-building event


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.