Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 364 Topic 37 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 364 Topic 37 Discussion

PMP Exam Topic 37 Question 364 Discussion:
Question #: 364
Topic #: 37

A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.

What should the project manager do first to prevent the project from going further off track?


A.

Perform a risk assessment and define a risk response action plan.


B.

Proceed with the project using management reserves to cover any delays or losses.


C.

Propose a pause in this phase to save labor costs and asset depreciation.


D.

Establish new partnerships with other suppliers in anticipation of any delays.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.