Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 364 Topic 37 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 364 Topic 37 Discussion

PMP Exam Topic 37 Question 364 Discussion:
Question #: 364
Topic #: 37

A construction project is in its final stage when the owner of a private property where the pipeline is routed refuses to collaborate. The lack of collaboration causes a project delay, but the client insists that the project must be completed as per the contract. What should the project manager do next?


A.

Request additional budget from the project sponsor and raise a dispute with the property owner to force them to collaborate.


B.

Use the contingency reserve, add more resources, and reroute the pipeline to complete the project as per the contract timeline.


C.

Escalate the routing pipeline issue to the project change control board (CCB) and wait for a resolution to the conflict.


D.

Review the agreement with the property owner, schedule a meeting with them to discuss their concerns, and inform the client.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.