PMI Project Management Professional (2025 Version) PMP Question # 360 Topic 37 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 360 Topic 37 Discussion

PMP Exam Topic 37 Question 360 Discussion:
Question #: 360
Topic #: 37

An agile team is brainstorming and prioritizing all of the risks according to severity. What should the team do about the identified risks?


A.

Mitigate the risks that are applicable to the current and following iterations.


B.

Focus on the project deliverables rather than the documented risks.


C.

Agree that any issue can be handled when it becomes a problem.


D.

Acknowledge that the risks will be handled in the corresponding iteration.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.