Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 360 Topic 37 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 360 Topic 37 Discussion

PMP Exam Topic 37 Question 360 Discussion:
Question #: 360
Topic #: 37

How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?


A.

Clarify project benefits with the sponsor.


B.

Identify the goal of each work product


C.

Perform integration testing of each release


D.

Include the entire project team in testing


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.