PMP Exam Topic 37 Question 360 Discussion:
Question #: 360
Topic #: 37

During the requirements gathering and analysis stage for the project, the team members are debating some functionality issues that are expected to be included in the scope. Due to this discussion, the planning activity for the scope definition is running late. What should the project manager do?


A.

Timebox the team members’ debate to ensure the activity is completed on time.


B.

Review expectations with all team members who are working on this activity.


C.

Discuss the issue with the team members who are delaying the activity.


D.

Ask team members to document all points that will need to be refined later.