PMI Project Management Professional (2025 Version) PMP Question # 347 Topic 35 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 347 Topic 35 Discussion

PMP Exam Topic 35 Question 347 Discussion:
Question #: 347
Topic #: 35

A project is nearing finalization and just released the final product to the customer. The assigned project manager left the company without notice and without sharing any information or documents for the remaining activities. A new project manager has just been assigned to the project.

What should the new project manager do next?


A.

Schedule a lessons learned meeting with the project team and close out the project.


B.

Use the contingency fund to extend the timeline and conduct a detailed review of past deliverables.


C.

Prepare a transition plan to hand over the operations and other closing documentation.


D.

Document the project manager's departure and the missing documents in the risk log.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.