Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 347 Topic 35 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 347 Topic 35 Discussion

PMP Exam Topic 35 Question 347 Discussion:
Question #: 347
Topic #: 35

A project manager has been managing a project for several months when an issue that had not been registered as a risk appeared. This issue may have a big impact on the project.

What should the project manager do?


A.

Delay the project until the issue is addressed and no longer presents as a risk to the project.


B.

Inform the sponsor that the issue has arisen and that the project's success may be uncertain


C.

Avoid managing the issue as it was not registered as a risk for the project and there is no planned response to it.


D.

Hold a meeting with the project team and relevant stakeholders to agree on the best way to manage the issue


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.