Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 345 Topic 35 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 345 Topic 35 Discussion

PMP Exam Topic 35 Question 345 Discussion:
Question #: 345
Topic #: 35

A project sponsor commonly asks the project manager to skip project retrospectives due to time constraints However the project manager persists in running this critical ceremony by reducing the time for preparation and for discussion

What are two issues that these actions by the project manager could cause? (Choose two)


A.

A lot of discussions that yield no results or possibly too many results


B.

A lack of direction and motivation for the team in the workshop


C.

Lessons learned from other teams to not be considered


D.

Time management plan for the retrospective workshop to not be updated


E.

A focus on the negative and a disinterest in further improvements


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.