Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 345 Topic 35 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 345 Topic 35 Discussion

PMP Exam Topic 35 Question 345 Discussion:
Question #: 345
Topic #: 35

A project management plan needs to be updated due to recent product requirements changes, but the latest version of the document is missing. What should the project manager do to prevent this from happening again?


A.

Improve the configuration management process


B.

Register an issue for the missing documents


C.

Ensure the lessons learned register is up to date


D.

Review the quality assurance (QA) processes


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.