PMI Project Management Professional (2025 Version) PMP Question # 345 Topic 35 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 345 Topic 35 Discussion

PMP Exam Topic 35 Question 345 Discussion:
Question #: 345
Topic #: 35

A project team is implementing an enterprise notification tool with a vendor. The project manager noticed that this vendor's developer has been reporting the same status for

several weeks in a row. A few days later, the vendor communicates that the deliverable will not be completed on time due to resource constraints within their company.

What should the project manager do next?


A.

Update the risk register to reflect the delay, communicate the impact to the schedule, and escalate to management for assistance.


B.

Conduct a project review with the project sponsor to explain the delay and add a developer to work with the vendor.


C.

Review the contract with the vendor to go over the financial penalty that is applicable to this situation.


D.

Add the delay to the issue log and work with the vendor for a resolution that will bring the schedule back on track.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.