Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 319 Topic 32 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 319 Topic 32 Discussion

PMP Exam Topic 32 Question 319 Discussion:
Question #: 319
Topic #: 32

A complex, high-value agile project includes sprint demonstrations with the customer

every four weeks. Executive management is concerned about the project's progress and

wants more frequent updates on the project status.

What should the project manager do?


A.

Inform executive management that the customer is made aware of the status duringthe sprint demo.


B.

Prepare a weekly status report and share it with executive management every week.


C.

Inform executive management about agile principles and processes that are followedin the project.


D.

Ask the team to prepare and share the status report with executive management everyweek.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.