PMI Project Management Professional (2025 Version) PMP Question # 319 Topic 32 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 319 Topic 32 Discussion

PMP Exam Topic 32 Question 319 Discussion:
Question #: 319
Topic #: 32

An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.

What should the project manager do?


A.

Add 4 additional weeks to the schedule and request additional resources.


B.

Ask the sponsor to obtain a special work permit to continue work.


C.

Review the project management plan to see the impact of the possible delay.


D.

Crash the resource management plan to keep the schedule on track.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.