Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 319 Topic 32 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 319 Topic 32 Discussion

PMP Exam Topic 32 Question 319 Discussion:
Question #: 319
Topic #: 32

A project team member finishes all assigned tasks in the middle of a sprint. The team member wants to plan tasks for the next sprint to deliver business value earlier. The team member has the abilities and knowledge to execute tasks not yet started by other team members in the current sprint. What should the project manager do?


A.

Validate completeness of the tasks delivered in the current sprint


B.

Increase team velocity to execute tasks for the next sprints


C.

Reassign the team member to other tasks in the current sprint


D.

Encourage the team member to execute the next sprint tasks


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.