A project manager has been asked by the human resources (HR) review team to share information about how the project team members interact, communicate, and conduct themselves to reduce the risk of conflicts and improve overall team performance.

What should the project manager do next?


A.

Provide the HR review team with the team norms document.


B.

Invite the HR review team to attend one of the daily standup meetings.


C.

Discuss the resource management plan with the HR review team.


D.

Direct the HR review team to the communications management plan.