Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 338 Topic 34 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 338 Topic 34 Discussion

PMP Exam Topic 34 Question 338 Discussion:
Question #: 338
Topic #: 34

After a project review meeting, a key stakeholder tells another stakeholder they do not trust the project status report. The second stakeholder approaches the project manager and mentions the conversation. What should the project manager do?


A.

Request the sponsor ask the key stakeholder to be attentive during the project review meeting


B.

Schedule a meeting with the key stakeholder to address the issue and obtain direct feedback


C.

Email the status report to all stakeholders and ask them to review and provide feedback


D.

Present the status report in a chart and assume everyone understands the report


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.