A project manager is leading the construction of a high-rise mall for a customer in an emerging competitive market. Some customers want to move in as soon as the ground floor is completed. What should the project manager do to deliver business value to the client?


A.

Use management reserve and crash the schedule


B.

Implement an agile project delivery approach


C.

Explain the need to follow the quality assurance (QA) schedule to the customer


D.

Adopt an incremental project delivery approach