Question #: 339
Topic #: 34

A project manager has completed an assessment of the project team's performance. Some team members have performed poorly on their assigned tasks.

What should the project manager do?


A.

Develop different approaches based on team members’ motivation and ability.


B.

Develop a standard approach to provide feedback to all team members.


C.

Provide intensive oversight to the team members who performed poorly.


D.

Create a new standard performance measure based on project requirements.