PMI Project Management Professional (2025 Version) PMP Question # 307 Topic 31 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 307 Topic 31 Discussion

PMP Exam Topic 31 Question 307 Discussion:
Question #: 307
Topic #: 31

A project manager is leading a project that is in the execution phase. Due to a company reorganization, some key project team members are likely to leave the project.

What should the project manager do next?


A.

Discuss this issue with the affected team members and support them during the transition.


B.

Start looking for replacements as soon as possible to help prevent any schedule slippage.


C.

Engage with the project sponsor to ensure that this change does not affect the project execution.


D.

Determine the impact to the project and implement mitigations per the project management plan.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.