Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 307 Topic 31 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 307 Topic 31 Discussion

PMP Exam Topic 31 Question 307 Discussion:
Question #: 307
Topic #: 31

A new manufacturing line project is planned to be delivered in iterations tor the equipment installation phase. During one of the iterations the vendor communicates to the project manager that they will not be able to deliver some of the equipment at the agreed dates.

What should the project manager do next?


A.

Replan the remaining iterations according to the new installation dates


B.

Update the product backlog m order to address the delays


C.

Review the procurement agreements to address the situation


D.

Find another vendor who can fulfill the delivery dates


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.