Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 4 out of 13 pages
Viewing questions 151-200 out of questions
Questions # 151:

A multiyear resource constraint project is midway through the execution phase. During a progress update meeting, it has been determined that there might be a schedule delay to deliver the project. The project manager has observed that all of the team members are working hard and lots of deliverables have already been completed.

What should the project manager do immediately about this situation?

Options:

A.

Ask the project planner to identify the critical path and respective delayed activities, and then investigate the reasons for the delay.


B.

Prepare a monthly report by highlighting the completed deliverables and communicate the delay to management.


C.

Register the schedule risk and present the new resources requirement to the change management board for schedule recovery.


D.

Ask the scheduler to update the schedule with the percent of work in progress (WIP) and communicate the results to the team.


Expert Solution
Questions # 152:

A project manager wants to assign a junior engineer to a new project. In past projects, the engineer showed initiative to take on complex tasks and solve problems in

innovative ways without any need for encouragement. However, the engineer declines the project manager's invitation to join the new project.

What is the most likely reason for the engineer's refusal to work on the project?

Options:

A.

The engineer did not feel welcome or enjoy working with the other project team members.


B.

The project manager did not follow the normal hiring process with the engineer's functional manager.


C.

The engineer has “project burnout" from working long hours and solving difficult problems.


D.

The project manager did not sufficiently support and recognize the engineer's professional growth.


Expert Solution
Questions # 153:

A project is currently in the execution phase. Because of the complexity of the project and the large number of regulatory requirements involved, the project manager decides to hold a management review with senior executives to ensure the successful implementation of project deliverables.

What should the project manager review during the management review to ensure the meeting is effective?

Options:

A.

The deliverables that are performing well and those that need more work.


B.

Metrics and key performance indicators (KPIs) that objectively reflect the status of deliverables.


C.

Potential changes to the project's strategy and the feedback from senior executives.


D.

Specialized reports created specifically for the meeting as per directions from the project sponsor.


Expert Solution
Questions # 154:

An urgent meeting has been established with the project team to discuss the cause of some quality issues that are preventing delivery to the client. The product owner recommends a root cause analysis (RCA).

What should the project lead do?

Options:

A.

Facilitate the meeting so anyone can share their ideas and is heard during the session.


B.

Allow the team to self-organize so one of the resources can lead the team to achieve consensus.


C.

Discuss the product owner's recommendations with the team and implement the agreed-on solutions.


D.

Discuss the recommendations with the test manager and request better quality control.


Expert Solution
Questions # 155:

A project manager is leading a cross-departmental project that involves many stakeholders. During the project, the project manager observes that the stakeholders are diverse and have different expectations about how the project should be handled. This leads to frequent confusion and misunderstandings among the stakeholders.

What should the project manager do to integrate the diverse stakeholder groups?

Options:

A.

Advise the team members to focus on project work and avoid getting distracted by the stakeholders’ disagreements.


B.

Hold separate meetings with the individual stakeholders and escalate their concerns to the project sponsor.


C.

Develop a joint quality policy for the project and seek a commitment by all of the departments.


D.

Analyze the probability and impact of the risks linked with the situation and implement the proper response plan.


Expert Solution
Questions # 156:

An agile project for a database migration impacts nearly all business units of the corporation. Every effort has been made to complete the migration before the end-of-support date for the database platform. A new impediment now implies the need to continue use of the old platform another year at a higher support price.

What should the product owner do about this situation?

Options:

A.

Reprioritize the backlog based on value and cost of delay divided by duration.


B.

Switch to a predictive approach to prevent any further delays to completion.


C.

Reprioritize the backlog based on story size and competence availability.


D.

Remove low-value items from the backlog to compensate for the higher cost.


Expert Solution
Questions # 157:

A large global organization developed a new medical implant that requires compliance with local government regulations. The approval process for one country is lengthy and will impact the intended launch date.

What should the project manager do?

Options:

A.

Organize an online distribution channel from another country.


B.

Ask the sponsor to authorize the launch and then wait for approval.


C.

Ask the board to use their influence and speed up the approval.


D.

Work with the team to find ways to bypass the regulations.


Expert Solution
Questions # 158:

A project team member, who is inexperienced in system development work is not performing well. Currently, there are no other staff members

available who are qualified to complete the work.

What should the project manager do?

Options:

A.

Assess the team member's development requirements and arrange for the team member to receive training.


B.

Seek approval from the project sponsor to use some of the project budget reserve to hire a new resource.


C.

Work with the functional manager to determine an incentive for the team member to complete the project.


D.

Request a substitute for the team member with a new resource who is more skilled in system development work.


Expert Solution
Questions # 159:

A customer's technical lead discussed a new feature with the project manager. The project manager believes the new feature will boost performance significantly and adds it as a high-priority item in the sprint backlog. At the end of the sprint, all of the planned stories were not completed because the new feature took more time.

What should the project manager do next?

Options:

A.

Agree with the project team to modify and delete some of the stories in the current sprint backlog


B.

Obtain approval from the project team and add the new story to the product backlog


C.

Receive an agreement from the product owner and add the new story to the product backlog


D.

Negotiate with the scrum master before adding the new story to the sprint backlog


Expert Solution
Questions # 160:

A project manager is assigned to a global project with dispersed team members. Previously, when working with remote teams, the project manager observed that team members do not tend to produce quality work.

What should the project manager do to ensure the project is completed on time with quality?

Options:

A.

Encourage the team to participate in a peer evaluation activity by the end of the project.


B.

Introduce the use of time sheets and ask team members to review and submit them regularly.


C.

Arrange regular team meetings for the team to update one another on the progress of their assigned tasks.


D.

Meet with the team together and in one-on-one meetings to set clear, shared targets.


Expert Solution
Questions # 161:

A credit collection company is implementing new software to assist customer service agents when calling clients for payments. The software will benefit the company by freeing up staff to work on other projects. Several business areas want to take advantage of this benefit.

What should the project manager do?

Options:

A.

Request all of the business areas to plan for a portion of the benefit equally and include it in their staffing plans.


B.

Set up a stakeholder session with all teams to agree and document the benefits and establish ownership.


C.

Ask the project sponsor for approval to distribute the project benefits equally to the business areas.


D.

Ask the project sponsor to make a decision on who will own the benefit and document the decision.


Expert Solution
Questions # 162:

A project manager is managing two integrated projects in a program A key integration point is misaligned, which has resulted in delays. One of the team's integration leads is a subject matter expert (SME) m this integration area. The other team's integration lead is not a SME but is more senior and has worked on the project longer Both team leads are blaming each other

What should the project manager do first to resolve this situation?

Options:

A.

Assign the resolution of the issue to the senior integration lead who has worked on the project longer


B.

Meet with both integration leads to understand the root cause and determine a resolution


C.

Escalate the issue to the program architect who developed the integration plan


D.

Assign the resolution of this issue to the integration lead who is a SME


Expert Solution
Questions # 163:

A project manager receives a suggestion from a team member for improving the product attributes without impacting the schedule or cost. This will add value to the project

and the customer.

What should the project manager do?

Options:

A.

Ask the team member to submit a formal change request.


B.

Accept the suggestion as it has no impact on the project.


C.

Ask another team member to validate the impacts of the suggestion.


D.

Reject the suggestion and ask the team member to focus on executing the plan.


Expert Solution
Questions # 164:

An agile project started 6 months ago. Since the beginning of the project, there have been disagreements among team members regarding daily meetings since some of the team members are not available at the same time. The project manager is convinced an agile team should be self-organizing, and that meeting times should be worked out by the team.

What should the project manager do?

Options:

A.

Establish a project schedule


B.

Assign a team leader


C.

Recognize the team's contributions


D.

Establish a team charter


Expert Solution
Questions # 165:

A project manager just completed the planning phase when a new stakeholder was assigned to the project. The deliverables were discussed with the customer, but the new stakeholder is still concerned about the benefits of two of the deliverables.

What should the project manager do next to address this stakeholder’s concerns?

Options:

A.

Review the benefits realization plan with the stakeholder.


B.

Provide the stakeholder with regular updates on project progress.


C.

Add the stakeholder to the stakeholder engagement plan.


D.

Review the prior analysis results with the stakeholder.


Expert Solution
Questions # 166:

A project manager at a large corporation has been assigned to oversee a customer experience project. Within the project, customer satisfaction is

a big issue and there are many unresolved customer queries on a daily basis. The project manager has been informed that the customer service

team is overwhelmed with these unresolved queries.

Which two actions should the project manager take to correct this problem? (Choose two)

Options:

A.

Contact the customers in batches and inform them that the issues are being worked on currently.


B.

Confirm the issues truly exist by conducting a survey and other analyses that may detect the real issue.


C.

Deploy solutions that will track, prioritize, and resolve queries as soon as possible.


D.

Ask senior management to replace the customer service manager with a more qualified one.


E.

Request that the customer service team prioritizes work on queries that are received this week.


Expert Solution
Questions # 167:

During the development of a project in a dynamic market environment, new unforeseen legal requirements have come into effect. The project

manager is not sure if some of the project deliverables will be fully compliant with the new requirements.

What should the project manager do?

Options:

A.

Stop the project until someone in the organization can identify all the new requirements and how they impact the project.


B.

Request the project management office (PMO) to assign a dedicated resource to monitor the external environment to enable more reactiontime.


C.

Agree with the project team that the new requirements will be applied to the next project, not the one already under development.


D.

Evaluate the consequences of noncompliance with relevant stakeholders and update the risk register with agreed actions.


Expert Solution
Questions # 168:

An agile project manager has started working in a company that builds shopping centers. The project manager wants to implement some agile

practices, which are relevant to the project.

What should the project manager do in order to gain buy-in from the different stakeholders?

Options:

A.

Organize a meeting with relevant stakeholders explaining the benefits of agile and the practices relevant for the project.


B.

Send the project management plan, which includes the suggested agile practices, to the stakeholders.


C.

Ask the project management office (PMO) to get buy-in from the stakeholders, because agile is an approach that differs from their previousways of working.


D.

Organize a meeting with a consultant to provide training to the stakeholders on agile practices.


Expert Solution
Questions # 169:

A project team member does not submit the project status report on time. The team member is frustrated about being required to complete the report. The team member believes that the report does not reflect the reality of the project, has too many pages, and will not be read by stakeholders.

What should the project manager do?

Options:

A.

Review the requirements of the report with the team member to redefine its purpose.


B.

Escalate to the team member's functional manager that the report was not submitted as requested.


C.

Instruct the team member to provide the report and document this in the performance review.


D.

Reassign the report to another team member to prepare and submit it as requested.


Expert Solution
Questions # 170:

A key project team member is out on sick leave in the middle of a critical project iteration. The project sponsor learns that any delay with the end-of-iteration release will displease the business stakeholders. Although all team members are cross-functional, they are also working close to full capacity.

What should the project manager do to address this situation?

Options:

A.

Discuss the issues with the sponsor to fully convey the problem of the unavailable resource and the amount of work being done. shared.


B.

Discuss this with the sponsor and hold a meeting with the stakeholders so all of the team challenges can be shared.


C.

Discuss this with the team so they can complete the work of the unavailable team member and aim for the release deadline.


D.

Discuss this with the team so they are able to reprioritize critical tasks and aim for the release deadline.


Expert Solution
Questions # 171:

At the end of a canceled project, the project manager sent surveys to all stakeholders. The survey also included templates for stakeholders to

outline situations, solutions, results, and suggestions.

How should the project manager use the information collected?

Options:

A.

Map the lessons learned against work breakdown structure (WBS) components.


B.

Archive the survey responses with project artifacts for future projects.


C.

Use the information to restart the project.


D.

Evaluate the information collected on areas of improvement.


Expert Solution
Questions # 172:

An organization's management system is being upgraded by an agile team. Although the project was scoped thoroughly, the functional requirements were handed over to the project team and there is no subject matter expert (SME) available to work on the project continuously. The project manager is concerned that the team's progress will be hindered by their lack of knowledge.

Which two project events will assist the project manager to ascertain if this is the case? (Choose two)

Options:

A.

Requirements analysis


B.

Retrospective


C.

Sprint planning


D.

Standup


E.

Backlog refinement


Expert Solution
Questions # 173:

A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.

What should the project manager do next?

Options:

A.

Add the new requirements to the project scope immediately since they are mandatory changes.


B.

Review the new requirements with the compliance department to determine if a change request is needed.


C.

Ignore the new requirements as the current budget and schedule do not allow for any changes.


D.

Proceed with the defined project requirements and delay implementing the new requirements.


Expert Solution
Questions # 174:

A new team member joins an agile team. In a previous role, this team member was a subject matter expert (SME). This team member often directs the team on how to solve problems based on previous experience.

What should the project manager do first?

Options:

A.

Update the definition of done (DoD) to include a review by the new team member to ensure the best outcome of each deliverable.


B.

Ask the new team member to create a wiki that the rest of the team can reference in the future for all questions.


C.

Ask the new team member to size all the stories in the backlog so that the rest of the team can focus on delivery.


D.

Let the new team member know that even if they know the answer, it is better to give the team a chance to solve their own problems


Expert Solution
Questions # 175:

A project manager is leading a fast-moving project with strict deadlines and minimal time to deliver each milestone. The project manager

discovers that one of the remote team members, who puts alot of effort into delivering the project, has confided in an on-site team member. The

remote team member feels they are not being adequately rewarded and recognized for their job.

What should the project manager do?

Options:

A.

Inform the human resource (HR) manager of this situation and ensure this news does not spread.


B.

Make arrangements with the resource's functional manager to relocate the team member to another existing project.


C.

Send a copy of the engagement contract to the remote team member and indicate that the team member is entitled to what is included in thecontract.


D.

Engage the remote team member, empathize with them, and let them know their contribution is appreciated regardless of their remote work status.


Expert Solution
Questions # 176:

During the execution of a project to develop a prototype, the customer asks the project manager to stop the prototype line and purge a specific

component based on recent reliability tests that have deemed the component to be deficient. The project manager checked the quality

management plan and there is no reference to this component.

What should the project manager do next?

Options:

A.

Inform the project sponsor of the situation and wait for the sponsor to provide further directions.


B.

Call a technical meeting with the customer to agree on a specification for the component and document it in the quality management plan.


C.

Submit a change request to proceed with the replacement of the component and wait for further customer instructions.


D.

Keep running the manufacturing line because there are no quality specifications for this component.


Expert Solution
Questions # 177:

A project manager has been authorized to begin a project and realizes that an effective high-performing team is needed to finish the project successfully. What should the project manager do next?

Options:

A.

Select members for their skill or potential.


B.

Establish the project scope and set clear team objectives.


C.

Set performance standards and direction.


D.

Hold early kick-off meetings and regular weekly meetings.


Expert Solution
Questions # 178:

A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed

for the product.

What should the project manager do to continue with the delivery plan and return to the expected velocity?

Options:

A.

Use retrospectives to better understand the new technology's impact on the schedule, map the skill gaps, and adjust the team accordingly.


B.

Reevaluate the backlog by looking for high-value/low-effort items, and negotiate a new minimum viable product (MVP) strategy with key stakeholders.


C.

Seek sponsor approval for additional funding to hire new team members, increasing the capacity of the team and compensating for the productivity lost with the new technology.


D.

Replace poorly performing team members with more experienced members, setting an example of accountability for the team.


Expert Solution
Questions # 179:

A medium-sized company has been exploring new marketing tactics with regard to launching a new product. New product creation is no small task. In the end, it was too big

of an expenditure for the company to undertake.

What should the project manager do in the future when working on new product projects?

Options:

A.

Make use of kanban boards so all stakeholders have a clear view of the project and provide their help accordingly.


B.

Increase the contingency reserve and prepare the team for applying fast-failing techniques when the estimates veer from the initial plan.


C.

Adopt a chain management approach, developing products based on the same platform and infrastructure.


D.

Train the team to first find the minimum viable product (MVP) that will deliver value to the customer.


Expert Solution
Questions # 180:

A senior vice president requested the creation of more agile teams to run projects of varying lengths and complexities in parallel with each other.

This will impact the amount of time the project managers will be able to dedicate to each project. The project managers typically dedicate 50% of

their time to projects regardless of their complexity.

What should the project manager do as a servant leader to help achieve this transformation?

Options:

A.

Review the organizational process assets (OPAs) to evaluate mitigation plans for similar risks.


B.

Create a risk entry regarding the project manager's capacity and develop a mitigation plan.


C.

Empower the team to develop the necessary skills to move the project forward independently.


D.

Issue a change request to hire additional project managers based on the increased workload.


Expert Solution
Questions # 181:

Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information

should the project manager provide so that senior management can get a broader view of the project?

Options:

A.

Risk register information


B.

Higher-level activities completed


C.

Milestones status report


D.

Resource breakdown structure (RBS)


Expert Solution
Questions # 182:

During a retrospective, one of the team members reports that a functional manager wants to be involved in task allocation. What should the project manager do?

Options:

A.

Inform the functional manager that self-organization includes task allocation.


B.

Confirm with the team members that the functional manager is responsible for the delivery.


C.

Ask the product owner to clarify the roles and responsibilities of the project team.


D.

Inform the functional manager that task allocation is the responsibility of the product owner.


Expert Solution
Questions # 183:

A project manager is leading a project that will be delivered using a Scrum framework. The organization has an innovative project management office (PMO) that fully supports agile and also has a very friendly procurement team. A new vendor needs to be engaged to provide more developers for a new reporting platform.

What should the project manager do?

Options:

A.

Use an agile approach and engage a vendor that delivered well in a previous organization.


B.

Consult the product owner and engage a vendor that is recommended by them.


C.

Consult the development team and engage a vendor that is recommended by them.


D.

Use a formal approach using procurement policies, procedures, forms, and work instructions.


Expert Solution
Questions # 184:

A project manager is assigned to an automotive product development project in me middle of the pilot phase. According to the test lab. a durability test was completed with good results 6 weeks ago but there were no reports left behind by the test engineer who left the organization the previous month.

What should the previous project manager have done to prevent this issue?

Options:

A.

Built a pair-engineering environment so that experienced engineers always work with junior engineers to assist in knowledge transfer


B.

Contracted with a third-party test lab to outsource all testing processes and required that they produce all test reports


C.

Led a technical benchmark workshop every month to share state-of-the-art technology trends and ask all team members to attend the workshop


D.

Built a shared repository for the project in the internal server and asked the team to create record and save all project deliverables to the server


Expert Solution
Questions # 185:

During the execution of a hybrid project, one developer had to be replaced. The new resource is extremely competent in quality assurance tasks, but does not have much

experience in development.

What should the project manager do?

Options:

A.

Allow the team to reevaluate the tasks and determine how they should be allocated.


B.

Maintain the same task allocation structure to avoid any disruption in the project team.


C.

Move the developer to another team and look for a replacement developer.


D.

Request that all quality assurance tasks be allocated to the new resource.


Expert Solution
Questions # 186:

A project manage is in the middle of an angle project comprised of 100 user stories broken down into five iterations. Each user story is worth U$$50. The actual expenditure is U$$2,00 and 50 user stories have been delivered.

Which statement is true?

Options:

A.

The project is over budget and behind schedule.


B.

The project is under budget and on schedule.


C.

The project is under budget and behind schedule.


D.

The project is on budget and on schedule.


Expert Solution
Questions # 187:

A project manager has been assigned to a new digital product line, which the company hopes will boost their revenue. The product is complex and requires customer feedback to continually refine the product. The project is being handled by a cross-functional agile team.

What should the project manager do to ensure value is delivered quickly?

Options:

A.

Plan the project to deliver value incrementally with regular releases.


B.

Request a budget increase to pay the subject matter experts (SMEs) more overtime


C.

Identify tasks that can run in parallel to deliver the project faster.


D.

Ask the project sponsor to provide additional resources to fast track the project.


Expert Solution
Questions # 188:

A project team began working on a complex project that involves new technology as a product. The team is new to the technology and the proposed approach. Additionally, the customer is apprehensive about how the product will be received in the market.

What should the project manager do to help the team and the customer?

Options:

A.

Manage the risks associated with the proposed approach.


B.

Assist the team with identifying the minimum viable product (MVP) to validate assumptions.


C.

Coordinate with the business unit to get detailed requirements.


D.

Work closely with the marketing team on market research and product segments


Expert Solution
Questions # 189:

A newly commissioned project has had trouble recruiting team members because the turnover rate is high. The human resource (HR) manager

has conducted several exit interviews. Many team members have expressed that the project manager has inadequate relationship management

competencies. The project manager explains that the exiting team members were lazy.

What should the project manager do to prevent this high turnover rate from continuing?

Options:

A.

Be more involved in the team member recruitment process to ensure qualified team members are chosen.


B.

Develop relationship skills as a leader and also develop the teams’ emotional intelligence skills.


C.

Avoid micromanaging the team, enforce stricter rules, and monitor employees.


D.

Explain to the recruiting manager that a project is temporary in nature, making it different than an operational environment.


Expert Solution
Questions # 190:

A project manager wants to ensure that the project acceptance criteria are met for all project deliverables. What should the project manager do to accomplish this?

Options:

A.

Schedule regular meetings with project stakeholders to make sure they are satisfied.


B.

Include project stakeholder expectations and needs while creating project acceptance criteria.


C.

Create a statement of work (SOW) and ensure it remains unchanged during the project life cycle.


D.

Discuss project acceptance criteria with the project sponsor before the execution phase.


Expert Solution
Questions # 191:

A project manager is developing a project baseline schedule and has started to

assign team members to the project activities according to their function. What should the

project manager do in this phase?

Options:

A.

Develop project onboarding guidelines for the team members assigned to the project.


B.

Ensure that a kick-off meeting is planned and invite relevant stakeholders toparticipate.


C.

Ensure that lessons learned are considered as part of the project scheduledecomposition.


D.

Confirm that no conflicts exist in resource calendars with assigned activities on otherprojects.


Expert Solution
Questions # 192:

A project manager's customer is new to agile approaches. When the customer found out that the project was going to use an agile approach, the customer became

concerned that the product quality will be sacrificed.

What should the project manager do?

Options:

A.

Ensure that the customer and the delivery team agree on the definition of done (DoD) in the beginning of the project.


B.

Invite the customer to join the daily standup meetings to better understand the product design and progress.


C.

Ensure the team demonstrates product features to this customer regularly to collect feedback and improve as needed.


D.

Invite the customer to join the regular sprint planning sessions to better understand the project's progress.


Expert Solution
Questions # 193:

After assigning tasks to a project team, a project manager discovers that some team members are uncomfortable. Same team members are having 4 difficult time understanding their assigned tasks, whereas other team members are challenging the schedule based on that allocation to the project.

Which phase of the Tuckman ladder of team formation is occurring?

Options:

A.

Forming


B.

Mourning


C.

Storming


D.

Norming


Expert Solution
Questions # 194:

A project manager has been assigned to a project where the budget is very tight. Incurring extra costs is not an option.

What should the project manager do to manage this situation?

Options:

A.

File a change request to make the customer billable for all extra costs incurred for the project.


B.

Ask the accounting department to forward all project expenses to the project manager's email.


C.

Monitor the budget for the project continually and anticipate any issues if possible.


D.

Ask the project resources to finish their assignments in less time than originally planned.


Expert Solution
Questions # 195:

During the setup of an agile project, the product owner expressed clear interest in

having features released during product development over having the product completed in

one year. What should the project manager do?

Options:

A.

Promote a productive environment where everybody can work without interruptionsfrom the rest of the team members.


B.

Create a reward system recognizing group contributions to get people motivated andimprove performance.


C.

Facilitate sprint planning sessions with a focus on defining the minimum viable product(MVP).


D.

Design a set of metrics including velocity, which is a good measure of value delivered.


Expert Solution
Questions # 196:

A large matrix organization is adopting a new communications approach. This is necessary because their projects often require the resourcing of expert knowledge in the form of specialists from various departments and divisions.

What should the project manager do to set up effective communications?

Options:

A.

Plan on transmitting the information in an easily understandable manner.


B.

Focus on the recipients’ needs and not the information itself.


C.

Use the highest possible technical language and avoid using metaphors.


D.

Ensure that messages sent to the recipients are delivered.


Expert Solution
Questions # 197:

A telecommunications company is doing a national network rollout involving continuously changing technical requirements. To address the situation the company has recently adopted a hybrid project life cycle. During a retrospective some team members complain that me majority of me stones are ready to test but have not advanced because they are waiting for the project manager's approval.

What should the project manager do?

Options:

A.

Update the issue log and review the lessons learned register for options


B.

Implement conflict resolution to accommodate the team's needs


C.

Implement decision-making techniques to advance the stones


D.

Empower the team to self-organize and make their own decisions


Expert Solution
Questions # 198:

A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is

seeking the project manager's recommendation on how to approach this request.

What should the project manager do to help the product owner?

Options:

A.

Provide an overview of the completed functionalities and release plan, and capture expectations for future stakeholder involvement.


B.

Invite the product owner to future demonstrations where they can provide feedback.


C.

Provide access to the latest user acceptance test (UAT) environment so they can see the solution.


D.

Remind the product owner of stakeholder accountability, and ask the product owner to determine the appropriate next steps.


Expert Solution
Questions # 199:

An insurance company is planning to make a big change to its core application. The project manager realizes there is resistance to change from the sales agents since they

are accustomed to taking orders manually and entering them in the system at the end of the day. With the new change, they will use point-of-sale devices to take orders online.

What should the project manager do to get commitment from the sales agents?

Options:

A.

Use a business case to model a sales pitch and gain consensus from the sponsors.


B.

Request help from the project sponsor to get support from the sales agents.


C.

Escalate the issue to senior management to gain team buy-in


D.

Explain the change benefits to the sales agents' manager to get their support.


Expert Solution
Questions # 200:

An organization is transitioning to an agile approach. At the project's first sprint review, the product owner did not accept the result of the sprint and has some concerns.

What should the project manager do?

Options:

A.

Organize a sprint retrospective and discuss the issues and how they can be avoided in the next sprint.


B.

Ask the project team to address the product owner's issues since the product owner is responsible for the scope in agile.


C.

Ask the product owner to accept the outcome since the team delivered what was agreed in the sprint planning.


D.

Create a record in the issue register and escalate the issue to the project steering committee.


Expert Solution
Viewing page 4 out of 13 pages
Viewing questions 151-200 out of questions