Questions # 151:

A sales team working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay. The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

Options:

A.

Have a discussion with the sales team to find a solution to the issue


B.

Validate the reason and add n as an issue m the issue log


C.

Escalate the issue to the functional manager


D.

Direct the sales team to speak with accounting to resolve the issue


Expert Solution
Questions # 152:

The product backlog has been completed and prioritized. and the first sprint has begun A team member advised that during the daily standup there is a delay in having an external vendor contract signed.

What is the project manager's priority in this situation?

Options:

A.

Request that the team member gel the contract signed as soon as possible


B.

Determine a mitigation strategy to move the project forward


C.

Take over contract negotiations for the team member to speed up the process


D.

Assist with the removal of impediments and blockers so that the project can continue


Expert Solution
Questions # 153:

A project is being delayed due to a large amount of rework caused by a quality problem that is impacting the critical path. What should the project manager do?

Options:

A.

Rebaseline the project schedule to absorb the delay.


B.

Report the delay with rectifying actions to the project management office (PMO).


C.

Notify the project steering committee about the cause of the delay.


D.

Report the delay with rectifying actions to the change control board (CCB) for review,


Expert Solution
Questions # 154:

A company's CEO complains about the frequency of project communications. The CEO receives five project reports each week by email but does not have enough time to review them. In addition, the information that the CEO receives is not relevant in that it does not explain the project status,

What should the project manager do first?

Options:

A.

Review the stakeholder engagement plan.


B.

Review the communications management plan.


C.

Send the CEO one executive summary per week instead of five reports per week.


D.

Meet with the team and decide the type and frequency of the reports to send to the CEO.


Expert Solution
Questions # 155:

An established project team with a good track record has been working on a project for one year The project manager trusts the team and the work they produce. Which term describes the project manager's management approach?

Options:

A.

Laissez-faire


B.

Transactional


C.

Transformational


D.

Charismatic


Expert Solution
Questions # 156:

An IT project manager has been referred to a new, highly rated vendor that provides quality assurance professional services, The project manager plans to engage the quality assurance vendor on a new project, but their rates do not fit into what was budgeted for the project.

What should the project manager do next?

Options:

A.

Discuss the issue with the management team.


B.

Engage the project stakeholders.


C.

Update the contract with a lower rate,


D.

Engage the procurement team.


Expert Solution
Questions # 157:

A company is implementing a project with team members who are located in different countries and lime zones Performance assessments show that team performance is low because the team doesn't have a common understanding about task distribution

What should the project manager do?

Options:

A.

Colocate the team members


B.

Perform team-building activities


C.

Review and reassign tasks


D.

Revisit the communications management plan


Expert Solution
Questions # 158:

A project manager is leading a new project that is in the initiation phase, The project will build a new type of software technology service that has never existed at the organization before and will reenginger the business process for several operations teams. The project manager needs to determine the project management approach to be used, and there are many team

members and stakeholders who have contradictory opinions.

What should the project manager do?

Options:

A.

Meet with the stakeholders to determine the approach using the project goals and desired outcomes.


B.

Leverage agile methods only as the project pertains to software implementation, which can be broken into increments.


C.

Leverage hybrid methods as the project has a blend of work that needs to bring in both agile and predictive methods,


D.

Determine what methods the team has been trained on and utilize those methods for the project.


Expert Solution
Questions # 159:

A project team has missed the delivery date for the West milestone of a large software development project protect governance dictates that formal communication be sent to project stakeholders including the project manager's supervisor when a milestone is missed. The project manager is concerned that this wilt reflect poorly on the team

What should the project manager do?

Options:

A.

Send a formal communication regarding the missed milestone


B.

Delay sending a formal communication until the project team catches up


C.

Ask for a meeting with the sponsor to decide whether to send the formal communication


D.

Forego the formal communication and have a conversation with the supervisor


Expert Solution
Questions # 160:

A project manager notices that one of the marketing executives in the firm always appears stressed. The project manager observes that the executive's performance is gradually declining and is affecting the project deliverables.

What should the project manager do?

Options:

A.

Assign the marketing executive's tasks to another project team member


B.

Review the executive's declining performance with human resources (HR)


C.

Show empathy and praise the marketing executive's strengths


D.

Make the marketing executive accountable for their work and output


Expert Solution
Questions # 161:

A sales learn working on an IT deployment project approached the project manager on several occasions and complained about nonpayment of their overtime pay The project manager realized that other team members are receiving their overtime pay

What should the project manager do next?

Options:

A.

Have a discussion with the sales team to find a solution to the issue


B.

Validate the reason and add it as an issue in the issue log


C.

Direct the sales team to speak with accounting to resolve the issue


D.

Escalate the issue to the functional manager


Expert Solution
Questions # 162:

A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not to release the requested staff. What should the project manager do first?

Options:

A.

Ask the leadership team for help obtaining the needed staff.


B.

Have a direct talk with the functional manager to understand the reasons behind their attitude.


C.

Evaluate the impact caused by the delay of forming the team and confront the functional manager.


D.

Check with human resources (HR) regarding the availability of staff.


Expert Solution
Questions # 163:

A project manager is working on a complex project with a high degree of change. What strategy should the project manager use to ensure a

successful project completion?

Options:

A.

Update the project management plan to reduce the possibility of scope creep.


B.

Schedule a regular risk review with the project management team.


C.

Increase the active engagement and participation of key stakeholders.


D.

Create a project change roadmap to keep track of all unforeseen changes.


Expert Solution
Questions # 164:

A global program is being kicked off, and various distributed teams are Involved in delivering the initiative. Besides planning and executing the scope for the initiative, team interactions must be considered.

How should the project teams interact in their meetings?

Options:

A.

Phone conversations


B.

Encrypted emails


C.

Videoconferencing


D.

Chat conversations


Expert Solution
Questions # 165:

we architects are unable to agree on how to approach certain components of the development that will be included In the upcoming sprint. After a one-on-one discussion, the architects have decided to each own a particular module of the system, and the team supports the decision.

What should the project manager do?

Options:

A.

Discuss the issue with the team to resolve the disagreement.


B.

Ensure that there is consensus among the project stakeholders.


C.

Discuss the issue during the next sprint planning meeting.


D.

Support the outcome of the architects’ agreement.


Expert Solution
Questions # 166:

One of the project manager's important assignments is to formally revise project compliance as it pertains to user data protection regulations. What should the project manager

do to monitor compliance?

Options:

A.

Assess the risk register.


B.

Conduct project reviews.


C.

Perform retrospectives.


D.

Complete sprint reviews


Expert Solution
Questions # 167:

During the execution of a construction project, the project sponsor asks to make

changes to the floor plan by adding a minimal storage room. The sponsor insists on making

this last-minute change, but they would like to avoid delays to the project.

Which document should the project manager refer to first?

Options:

A.

Change management plan


B.

Schedule management plan


C.

Scope management plan


D.

Cost management plan


Expert Solution
Questions # 168:

A production team will soon begin their first agile project. No one in the team or management has agile knowledge. The training manager can only fund three enrollments.

Match the team role on the left to the correct training course on the right. (Use all three of the team roles.)

Question # 168


Expert Solution
Questions # 169:

A project team strongly encourages the project manager to purchase an application that will significantly reduce work time. Without the application, the deadline might be missed. However, the purchase will impact the project cost. The sponsor would like to explore a less expensive application that will save the team's time.

What should the project manager do?

Options:

A.

Raise a change request.


B.

Purchase the application.


C.

Create a decision tree.


D.

Analyze assumptions and constraints.


Expert Solution
Questions # 170:

Companies A and B are codeveloping a cutting-edge technology product. Based on customer feedback, the marketing department urgently requests a new feature in 2 weeks. Company A's front end is ready, but company B requires 4 weeks to deliver the complete back end and is busy with the current release.

What should the project manager do to obtain agreement from both companies and acceptance from marketing?

Options:

A.

Create a special release 4 weeks after the current release to deliver the new feature in its entirety.


B.

Stop the current release work for 4 weeks in order to work and deliver the new feature completely.


C.

Plan the delivery of a minimum viable feature in 2 weeks to enable early showcasing of business value.


D.

Add the new feature to the list for the next release and continue working on the current release.


Expert Solution
Questions # 171:

Clients are complaining about the delay on a product delivery timeline. It is confirmed that the issue is related to the product inventory and availability.

What should the project manager do to engage the stakeholders?

Options:

A.

Ask the team to work on the complaint raised by the clients.


B.

Escalate the issue raised by the clients to the project sponsor,


C.

Develop a solution with the team to identify the inventory level.


D.

Work with the team and the product owner to define the next steps.


Expert Solution
Questions # 172:

An agile team has been assigned to a project that mandates the implementation of changes to key government products. The team has been given 6 months to fulfill this mandate.

What should the team lead do next?

Options:

A.

Create all of the stories just for the next sprint and skip the epics until the next sprint.


B.

Create the epics at a high level for the requirements and begin grooming sessions.


C.

Create the project charter and statement of work (SOW) to estimate the changes and the scope of the change.


D.

Create all of the stories needed to fulfill this change, document them in the backlog, and prioritize them according to business value.


Expert Solution
Questions # 173:

An unforeseen event has shut down public works projects for 4 weeks. Activities on the critical path will fall behind based on the project schedule.

What should the project manager do?

Options:

A.

Add 4 additional weeks to the schedule and request additional resources.


B.

Ask the sponsor to obtain a special work permit to continue work.


C.

Review the project management plan to see the impact of the possible delay.


D.

Crash the resource management plan to keep the schedule on track.


Expert Solution
Questions # 174:

A project had scheduling delays, which necessitated the team to work overtime to meet critical milestones. This led to some misunderstandings

among team members. The project sponsor has allocated a monetary award.

How should the project manager utilize the award?

Options:

A.

Meet with the team members and ask them how to spend the reward.


B.

Arrange a luncheon for all team members and include team-building sessions.


C.

Draft a points system to allocate a portion of the money for each resource.


D.

Allocate the reward to the team leaders to spend on the team as they see fit.


Expert Solution
Questions # 175:

A project manager is leading a project in which the product requirements have not been fully met due to several uncertainties about customer acceptance. What should the project manager do?

Options:

A.

Gather a reduced number of approved requirements and add some extra features to fulfill the product specifications.


B.

Ask team members to research and collect data about the best features offered by similar products in the market.


C.

Stop all project activities until all requirements are set up front by the project sponsor and the key stakeholders.


D.

Gather enough requirements to produce a minimum viable product (MVP) with which to evaluate customer acceptance.


Expert Solution
Questions # 176:

A company must implement a new regulation. The government has specified the date when the regulation will be enforced but has only provided high-level information on

the regulation's requirements. Therefore, changes in definitions are to be expected due to uncertainty.

Which life cycle should the project manager use for this project?

Options:

A.

A predictive execution strategy


B.

A hybrid execution strategy


C.

An iterative execution strategy


D.

An agile execution strategy


Expert Solution
Questions # 177:

A project manager is part of an organization that is assessing the use of agile delivery approaches. A new project management office (PMO) manager who had a bad experience with a Scrum approach recommended that the project board replace Scrum with a predictive approach.

What should the project manager do?

Options:

A.

Define a risk management plan (or the new approach, as needed.


B.

Review the benefits realization plan to include the cost of the change.


C.

Define a project management plan for the new approach, as needed.


D.

Review the communications management plan to identity new stakeholders.


Expert Solution
Questions # 178:

A project manager has been assigned to a new project that will be delivered using an agile framework. The sponsor is asking for a cost estimation to build the business case.

What should the project manager do?

Options:

A.

Ensure the client representative is involved in the estimation.


B.

Review the completion costs of similar projects.


C.

Ensure that a 20% contingency is included in the estimation.


D.

Review the lessons learned from similar projects.


Expert Solution
Questions # 179:

A project manager is leading a project that includes several organizations with unique corporate cultures. These diverse corporate cultures are affecting project expectations. The varying expectations often lead to conflicts, which often require the project manager's involvement.

What should the project manager do first to evaluate the cultural differences within the organizations?

Options:

A.

Establish a probability and impact matrix and plan response criteria.


B.

Disregard the situation since it is not hindering the project deliverables.


C.

Develop a joint policy among the various organizations.


D.

Escalate the issue to the project sponsor and seek their guidance.


Expert Solution
Questions # 180:

In an agile project, the team is disagreeing about which user story to complete first. One is technically complex and long to complete. The second is a lower priority but easy to complete.

What should the project manager do?

Options:

A.

Have the team complete the technically complex story first.


B.

Work with the product owner to clarify and prioritize the backlog stories.


C.

Have the team complete the less complex story first.


D.

Work with the agile coach on the user stories to avoid conflict.


Expert Solution
Questions # 181:

A project team is transitioning from a predictive to an agile approach. The project manager is trying to minimize the support issues that the product has had in production.

One particular pain point is the transition to operations, where the issues usually arise.

What should the project manager do to improve this scenario?

Options:

A.

Increase the focus on backlog items that cover support requirements, as well as product manuals and operation guides.


B.

Ask the support/operation team to participate in the daily standup meetings to contribute to the project's progress.


C.

Engage the operation teams in the retrospectives and demo sessions and incorporate their feedback on project activities.


D.

Foster stakeholder participation by engaging them early on the backlog discussions.


Expert Solution
Questions # 182:

A project is on its fifth iteration out of six. One member of the team has left the company unexpectedly.

What should the project manager do next?

Options:

A.

Detail the reason for the project delay in the status report.


B.

Invite the stakeholders to discuss a mitigation plan.


C.

Take on some of the necessary work to minimize the impact.


D.

Register an issue and escalate it to the project sponsor.


Expert Solution
Questions # 183:

A project team is conducting sprint planning. Based on the estimated effort, only 95% of the items included in the sprint may be delivered. The product owner asks the project manager for advice on how to prioritize the backlog items.

What should be used to prioritize the backlog items?

Options:

A.

Risk to delivery


B.

Technical complexity


C.

Business value


D.

Estimation accuracy


Expert Solution
Questions # 184:

An organization embarking on a significant transformation initiated a project to improve and document business processes. One of the objectives of the project is to implement agile project delivery.

What is the main reason for adopting agile?

Options:

A.

Projects will be completed faster, saving time and money.


B.

Projects will deliver early and use value based on priority.


C.

Projects will be delivered with very low risk to the organization.


D.

Projects will be delivered with significant cost savings.


Expert Solution
Questions # 185:

During iteration two of a project with two teams {A and B), the project manager is concerned that there are two critical activities from team A that must be started in iteration four. Additionally, these two activities are dependent on an activity from team B that has not yet been prioritized.

What should the project manager do?

Options:

A.

Ensure team B prioritizes the dependent activity in iteration three.


B.

Include the dependent activity in the current iteration for team B.


C.

Assign the two critical activities to team B in iteration two.


D.

Cancel the current iteration and reschedule it with the dependent activity.


Expert Solution
Questions # 186:

A vendor project manager and team are implementing a software solution across the organization. A customer stakeholder who was not present during the sales process is demanding that the team implement requirements that are out of scope without adding additional cost to the project.

What should the project manager do next?

Options:

A.

Escalate the issue of the additional requirements to the executive leadership team.


B.

Refer the stakeholder to the delivery specifications in the statement of work (SOW).


C.

Implement all the requirements the customer has requested.


D.

Adjust the scope baseline and schedule baseline accordingly.


Expert Solution
Questions # 187:

The team lead on a project has left the organization and management wants to promote engineer A to this position. The project manager is confident that selecting engineer A will add problems to the project and believes that engineer B would better fit this role. The project manager discussed all of the arguments with management but their decision remains unchanged.

What should the project manager do?

Options:

A.

Help engineer A to become familiar with this new role and ensure engineer B stays motivated.


B.

Promote engineer B instead since the project manager has the authority to make this decision.


C.

Request management approval that engineer B will be promoted if engineer A fails in this role.


D.

Coach engineer B to be prepared to perform this role if and when engineer A fails.


Expert Solution
Questions # 188:

A project manager is leading a global team that they have worked with in the past and has a high level of trust with them. The team is located in different countries and time zones and will need decisions in a timely manner.

In order to ensure that the project runs smoothly across the team, how should the project manager approach delegation?

Options:

A.

Delegate most authorities and control the authority by withholding important information.


B.

Delegate certain authorities and control the authority by withholding important information.


C.

Delegate certain authorities and share information to allow fair decision-making.


D.

Delegate most authorities and share information to allow fair decision-making.


Expert Solution
Questions # 189:

A project manager has just received communication from an operational functional manager to complete an additional scope item for a project that was formally closed a few weeks ago. The scope looks relatively small and simple to handle as part of the daily operations activity.

How should the project manager deal with this request?

Options:

A.

Submit a change request and allocate the budget and resources needed for execution.


B.

Confirm that the budget and resources are available to execute the work request.


C.

Check the alternative resources available in the organization for the request.


D.

Evaluate the nature of the request and plan communication accordingly.


Expert Solution
Questions # 190:

A project manager prepared a project benefits management plan. Which of the following should be included in this document?

Options:

A.

Project requirements, target benefits, issue log, metrics


B.

Target benefits, strategic alignment, time frame for realizing benefits


C.

Strategic alignment, benefits owner, risk register


D.

Target benefits, benefits owner, lessons learned


Expert Solution
Questions # 191:

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing protect Based on that information, the project manager believes the project should be stopped

How should the project manager handle the situation?

Options:

A.

Remove the items no longer applicable from the backlog and present the backlog to the project team


B.

Continue working on the defined scope and review the risk matrix


C.

Have a discussion with the project sponsor and cancel the project


D.

Have a discussion with the sponsor and recommend the project business value be reassessed


Expert Solution
Questions # 192:

A project manager is looking for ways to keep the budget on track throughout the project life cycle.

What should the project manager do to ensure that happens?

Options:

A.

Evaluate and test all budget variances.


B.

Baseline the project budget and schedule.


C.

Prioritize high-cost tasks and monitor them.


D.

Use metrics to track the cost performance.


Expert Solution
Questions # 193:

A highly critical project is in jeopardy due to missing professional resources. What should the newly assigned project manager do first?

Options:

A.

Find available professionals within the organization to fill the gaps.


B.

Allocate funding for seeking external professionals to fill the gaps.


C.

Determine the possibility for team members to split up the required tasks.


D.

Request additional budget for team training for the missing expertise.


Expert Solution
Questions # 194:

A team has developed and tested new software to control airplanes during flights. There are several regulatory requirements that must be met. What should the project manager do to meet these requirements?

Options:

A.

Determine potential threats regarding compliance with the regulations.


B.

Ask human resources (HR) to assign a compliance specialist to the team.


C.

Validate that the software is compliant with standards and regulations.


D.

Measure the extent to which the project complies with the regulations.


Expert Solution
Questions # 195:

A project manager is reviewing several potential changes to the contract with third-party vendors.

Which two changes could trigger a modification to the vendor contractual obligations? (Choose 2)

Options:

A.

Adding new resources to the change control team


B.

Adding vendors to increase flexibility and availability of work crews


C.

Introducing additional requirements based on new regulations


D.

Modifying a supplier's name due to a vendor acquisition


E.

Replacing a material type based on product availability


Expert Solution
Questions # 196:

A primary stakeholder is unable to join the project status meetings consistently. The project manager has been communicating with this stakeholder informally and regularly

to ensure that the stakeholder is up to date on the project. However. the project manager has recently resigned and will not be meeting with the new project manager prior to

departure.

How should the project manager ensure that the new project manager continues to update this particular stakeholder?

Options:

A.

Update the communications management plan with specific information on stakeholder engagement.


B.

Update the stakeholder engagement plan with the specific communication needs for the stakeholder.


C.

Ensure that the project team has been provided guidance on the specific needs of this stakeholder.


D.

Ensure that the project documents contain specific instructions regarding the stakeholder.


Expert Solution
Questions # 197:

A project manager is assigned to a regulatory project for their country. The deadline for delivering results in compliance with the new laws is very tight, and the project team members have not yet been assigned. One of the project manager's peers informs the project manager that a project with the same scope for a different country was completed 1 year ago.

What should the project manager do first?

Options:

A.

Register a new risk in the risk management plan.


B.

Ask for additional resources and review the project estimate.


C.

Review organizational process assets (OPAs) and perform analogous estimating.


D.

Complete a bottom-up estimation for the project activities.


Expert Solution
Questions # 198:

A client from the travel and hospitality industry is building software for an ongoing project. The project sponsor and key project stakeholders ask to add four new functionalities to the upcoming sprint.

What should the product owner do next?

Options:

A.

Ask the team to start implementing the new tasks.


B.

Add the new tasks to the current sprint backlog.


C.

Request a change control to expand the scope with the new tasks.


D.

Prioritize the new tasks in the planning of the upcoming sprint.


Expert Solution
Questions # 199:

A customer has provided excellent feedback on the project. However, a key project resource is leaving the company.

Which measure should mitigate the impact of this key resource's departure?

Options:

A.

Offer a new contract to the resource who is leaving.


B.

Establish a proactive knowledge-sharing plan.


C.

Update the risk register and inform the customer.


D.

Develop a contingency budget to replace the key resource.


Expert Solution
Questions # 200:

An organization is using a hybrid delivery approach for a business project. The product owner, the person who was also managing the project, was promoted to a more senior role. A new project lead has joined the project.

Which artifact should the project lead use to ensure that the project benefits have been identified?

Options:

A.

Solution architecture


B.

Product backlog


C.

Statement of work (SOW)


D.

Business case


Expert Solution