Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 4 out of 12 pages
Viewing questions 151-200 out of questions
Questions # 151:

The project sponsor recently requested that a vendor begins working toward adopting a hybrid approach. In response, the vendor hired a project manager experienced in agile for the project.

What does that project manager need to do to make the team work in a collaborative way?

Options:

A.

Request the project management office (PMO) for a team of mentors.


B.

Allocate time to mentor the team.


C.

Update the issue log.


D.

Identify any training gaps


Expert Solution
Questions # 152:

A project manager is in a learn meeting and the project team requires a decision to be made about a new suggested timeline due to an impact from a potential scope change What should the project manager do?

Options:

A.

Make the decision on behalf of the organization


B.

Review the stakeholder map along with the organizational chart and delegate the most senior person to make the decision


C.

Schedule a project decision meeting with all stakeholders to discuss the decision.


D.

Follow the stakeholder engagement plan


Expert Solution
Questions # 153:

A project manager is approaching the end of a project, and several tasks are now practically complete and ready for handover to the client How should the project manager proceed?

Options:

A.

Update the quality management plan for the overall project


B.

Ask the client to verify and accept the tasks that have been completed


C.

Close out the project tasks that have been completed


D.

Update the communications management plan for the overall project


Expert Solution
Questions # 154:

A project manager has a team of shared resources from other projects who are working on a client project Three days before the project is due. The team informs the project manager that the project will be delayed because a component was not delivered on time Competing priorities of the shared resources are delaying delivery of the component

What should the project manager have done to prevent this delay from happening?

Options:

A.

Updated the risk management plan and registered lessons learned for the project


B.

Reorganized the team for the project based on the work breakdown structure (WBS)


C.

Maintained constant communication with the stakeholders of the other projects


D.

Used the resource management plan to identify the impacts of the other projects


Expert Solution
Questions # 155:

A new project manager is assigned to lead an agile project The project manager wants to use motivation to encourage the team to perform well throughout the project

What should the project manager do?

Options:

A.

Use the management reserves to fund some team-building activities


B.

Inflate project estimates to provide a financial buffer for team activities.


C.

Find another method to increase the team's performance


D.

Implement a reward system aimed to keep the team engaged and motivated


Expert Solution
Questions # 156:

A project manager joins a team that is providing a customized enterprise resource planning (ERP) system to a client A potential design problem is identified by the development team After reviewing this issue with the project owner and team members, all agreed to revise the design to avoid a system defect when deployed The design is already approved.

What should be the project manager's next steps?

Options:

A.

Conduct a proof of concept to make sure there are no problems in the revised design


B.

Amend the design specifications and pass them to the development team for reprogramming


C.

Make a change request and get format approval from the project owner


D.

Inform the client of the problem and follow the change request process


Expert Solution
Questions # 157:

During daily calls team members share task progress One team member does not usually communicate many details and has critical tasks to be completed All team members are located in different countries and critical work is about to start Which two options will help the project manager in this situation? (Choose two)

Options:

A.

Encourage all team members to use a virtual workspace


B.

Ask the team to send emails with detailed task progress


C.

Talk to the team member about their engagement and take appropriate action.


D.

Reassign the work to a resource who participates in the daily calls


E.

Report the team member’s poor performance to the functional manager


Expert Solution
Questions # 158:

A project manager for a strategic initiative realizes a new stakeholder is interested in the project and wants to ensure the stakeholder is fully aware of the goals, objectives, benefits, and risks of the project. What should the project manager do to enhance the success of the project?

Options:

A.

Add the new stakeholder to the communications management plan


B.

Share the project status reports with the new stakeholder.


C.

Update the stakeholder engagement plan


D.

Schedule a meeting with the new stakeholder


Expert Solution
Questions # 159:

A team has been working on a project for several months,, but the completion date is unclear because the scope is changing frequently as new knowledge is gained. Some deliverables have already been completed, but when new stakeholders join the team, they complain that project outcomes are not meeting business goals.

How can the project manager prevent this situation from happening in the future?

Options:

A.

Create a prioritized backlog and define iteration review sessions with stakeholders


B.

Create a detailed work breakdown structure (WBS) and milestone schedule approved by all stakeholders


C.

Schedule a daily meeting to review team performance and impediments


D.

Schedule a kick-off meeting for every project phase to share the project management plan with all stakeholders


Expert Solution
Questions # 160:

During initiation of a new product improvement project, a project manager finds historical data showing that a similar project resulted in customers complaining of an even worse user experience compared to the previous product version

How can the project manager prevent this outcome in the new project?

Options:

A.

Hire a team of external users to perform acceptance testing on the product.


B.

Define a user focus group as external stakeholders with a high influence on outcomes


C.

Hire a consultant to perform a benefit analysis as an input to the project charter.


D.

Define a high-level risk and plan mitigation after completing the work breakdown structure (WBS


Expert Solution
Questions # 161:

Which three of the following scenarios are impediments to which a scrum master should pay attention? (Choose three)

Options:

A.

A team member talking about a user story that is not on the Scrum board


B.

A team member talking about a user story that is on the Scrum board


C.

A technology that blocks agile capabilities


D.

A lack of team empowerment and an inability to self-organize


E.

A review of the backlog at daily standup meetings


Expert Solution
Questions # 162:

After a meeting with the customer, the project manager receives special recognition because the project is always on schedule Later that day, the project manager attends a regular project team meeting to follow up on the status of the deliverables.

What should the project manager do in the project team meeting?

Options:

A.

Share the customer feedback with the project team


B.

Follow the meeting agenda and make a list of the next deliverables


C.

Document this feedback in the meeting minutes.


D.

Start planning how to improve the dates of next deliverables


Expert Solution
Questions # 163:

The project manager started a new project and must ensure that the team members and stakeholders are adequately trained. After an interview with the team, the project manager discovers that all resources have experience in different agile methodologies

What should the project manager do?

Options:

A.

Make sure the project team is aware of all agile techniques


B.

Skip the training because the team already understands agile


C.

Ensure the team has a common understanding of agile


D.

Teach one agile methodology fully and completely


Expert Solution
Questions # 164:

A company has decided to implement a new archiving system A data breach occurred during the implementation of the project

What should the project manager do first?

Options:

A.

Implement the planned risk response to handle the issue.


B.

Review possible alternative documentation methods with team


C.

Update the risk register with the risk and proposed impact.


D.

Ask the team to fix the system to resolve the issue


Expert Solution
Questions # 165:

A project manager is tracking a project, but a key stakeholder will not accept the project's key performance indicator (KPI) results Which tool or technique should the project manager use?

Options:

A.

Autocratic decision making


B.

Expert judgment


C.

Context diagram


D.

Change control tools


Expert Solution
Questions # 166:

A new resource has joined an iterative project team The project manager notices that the resource is unable to complete the deliverables on time

How should the project manager address this situation?

Options:

A.

Address the lack of performance by coaching the new team member


B.

Discuss options to improve performance with the resource manager


C.

Provide performance feedback as part of the retrospective ceremony.


D.

Request a more efficient replacement resource from the project sponsor


Expert Solution
Questions # 167:

The project manager has observed that two team members have been arguing with each other openly at meetings To push their ideas through, each team member individually spoke with the sponsor directly and made decisions without informing the project manager or other team members

What two actions should project manager take? (Choose two)

Options:

A.

Ask the team members to work it out themselves


B.

Discuss this situation with other project managers and ask for advice


C.

Reiterate ground rules at the next meeting and ensure that all team members are clear about these rules.


D.

Address the behavioral issue with each team member


E.

Discuss the behavior directly with their managers and request them to correct the behavior.


Expert Solution
Questions # 168:

A project manager has received an updated earned value analysis report The following are the key findings from the report

•Budget at completion = USS1 million

•Earned value = US$0 7 million

•Actual cost = US$0 75 million

•Cost performance index = 0 933

Based on this information, what should the project manager conclude about project performance'?

Options:

A.

The project will be completed exactly as planned


B.

The project will be easier to complete than planned


C.

The project will be difficult to complete as planned.


D.

The project will not be completed as planned


Expert Solution
Questions # 169:

A project in the execution phase is behind schedule and is missing some materials The contractor submits an offer to supply the missing materials and reimburse the cost since the internal procurement process will cause more delay The project manager does not agree with the costs submitted by the contractor for the missing materials

What should the project manager do next?

Options:

A.

Ask the project sponsor to allocate more budget to cover the costs


B.

Update the procurement management plan and negotiate with the contractor.


C.

Ask the contractor to review the offer and reduce the costs.


D.

Update the procurement strategy and negotiate with the contractor


Expert Solution
Questions # 170:

A project manager accepts a delivery at the project site but the items are of a poor quality The project manager gets the local vendor to fix the items but more deliveries from this vendor are expected

What should the project manager do going forward?

Options:

A.

Allocate extra time to inspect deliveries for quality assurance upon arrival at the site


B.

Review the contract requirements and ask for the applicable evidence for quality assurance


C.

Have the vendor issue the quality documentation prior to the next delivery.


D.

Call the vendor and have them verbally guarantee the quality of the next site delivery


Expert Solution
Questions # 171:

The project team follows a hybrid framework for its delivery. During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements

How should the project manager address this situation?

Options:

A.

Ask the team to include the compliance requirement in the current sprint and deliver it.


B.

Add the new compliance requirement to the backlog as the technical team does not have any capacity.


C.

Include the compliance lead in the stakeholders list and wait for the next status meeting


D.

Collaborate with the compliance team member to review and prioritize the requirement’s delivery


Expert Solution
Questions # 172:

The following table shows the business value created and the development effort required to implement various features in a product

Question # 172

Which feature should the team prioritize first? Enter the feature name in the box below

Question # 172


Expert Solution
Questions # 173:

After reviewing the project management plan with key stakeholders, the project manager was told that an 18-month release plan was unacceptable and the product should launch in six months. Based on the new timeline, what should the project manager do?

Options:

A.

Plan for overtime, apply crashing and fast tracking and share the risk of failure with project stakeholders.


B.

Review the project backlog looking for high-priority items and come up with a minimum viable product (MVP) that fits the expected timeline


C.

Seek approval with the sponsor to triple the project budget, hiring more people to

compensate for the compressed schedule


D.

Go over the critical path with stakeholders, explaining why it is not possible to deliver all the scope in the expected timeline


Expert Solution
Questions # 174:

A company was awarded a project in a dangerous location that poses several high-level risks for employees Help is needed to tram the employees on major safety and health factors The project is ongoing and uses a hybrid approach The project will be conducted in multiple sites, with several development iterations running in parallel

How should the project manager handle this situation?

Options:

A.

Allocate and use part of the project's contingency reserves for training purposes.


B.

Negotiate a contract and form a partnership with a local authority for medical and security support services.


C.

Perform a retrospective and update the risk register and resource management plan regarding the necessary budget for training


D.

Hire only local resources who are aware of the terntory's hazards, providing employment to the local community


Expert Solution
Questions # 175:

A project manager is managing a hybrid project. After attending an iteration review, a stakeholder tells the project manager that they are very busy and asks why these reviews are held so frequently Record the issue in the issue log and escalate the conflict to the project sponsor for assistance.

How should the project manager respond’

Options:

A.

Negotiate a reduced review attendance with the stakeholder and update the stakeholder engagement plan to reflect this reduced


B.

Discuss with the stakeholder the benefits of the hybrid project and how frequent reviews lead to greater value and less rework


C.

Record the issue in the issue log and escalate the conflict to the project sponsor for

assistance


D.

Explain to the stakeholder that the stakelrolder engagement plan requires their attendance at all reviews


Expert Solution
Questions # 176:

A new team member has joined an agile project, replacing a team member who recently left The project team needs the new team member to speed up their ability to contribute effectively to the project

What should the project manager do to help in this situation?

Options:

A.

Assign the new team member the same tasks that were assigned to the previous team member who they replaced


B.

Schedule knowledge transfer sessions and assign less complex tasks to the new team member


C.

Send technical documentation to the new team member and schedule training for the next iteration.


D.

Have the new team member complete all of the company’s mandatory training


Expert Solution
Questions # 177:

A project manager is worried that a key stakeholder is not participating in the project and has concluded that the final product is not as good as it could have been if the stakeholder had been more involved Drag the scenario on the left to the correct risk response strategy on the right

Question # 177


Expert Solution
Questions # 178:

During the course of a project, a junior team member approaches the project manager for some direction and advice on risk mitigation How should the project manager respond?

Options:

A.

Tell the junior team member that the information is available in lessons learned


B.

Offer guidance and follow up with some developmental activity for the junior team member


C.

Inform the junior team member that risk mitigation is not part of their work


D.

Refer the junior team member to the senior team member who develops the risk mitigation strategy


Expert Solution
Questions # 179:

During the implementation of a project the project team discovered a new opportunity After an internal review the project team agreed that the opportunity is outside of the project scope The project manager decided to update the risk register and escalate the opportunity to a higher level

What should the project manager do next with this opportunity?

Options:

A.

Share this opportunity with another project


B.

Establish a contingency reserve to support the opportunity


C.

Further monitor the opportunity


D.

No more action is required


Expert Solution
Questions # 180:

The customer is reviewing the new reporting system and informs the project manager that one of the components in the printing module is not complete The project manager reviews the work breakdown structure (WBS) and confirms that the component Is included.

What does the project manager need to do first?

Options:

A.

Raise a change request to immediately implement the printing module component.


B.

Escalate this issue to the project sponsor immediately


C.

Ask the project team to conduct a quality audit of the printing module components.


D.

Meet with the project team to understand the issue and define actions.


Expert Solution
Questions # 181:

An agile project manager would like to convert the requirements document into epics, capabilities, features and stories In how many iterations should the project manager estimate the story duration?

Options:

A.

Four iterations


B.

One iteration


C.

Two iterations


D.

Three iterations


Expert Solution
Questions # 182:

After gathering all the requirements for a project with dependencies on external stakeholders, the project team is finishing the second iteration At this point, the project manager learns about a possible change in regulations that would prevent the product launch

What should the project manager do to realize benefits?

Options:

A.

Add an entry in the risk log


B.

Implement the changes


C.

Review target benefits.


D.

Improve the team's velocity


Expert Solution
Questions # 183:

During project execution, the project manager notices that the work performance reports have deteriorated drastically in less than two weeks The project team in country A is complaining about delays resulting from holidays occurring in country B that have impacted their project team

How should the project manager handle this situation?

Options:

A.

Implement crashing to compress the schedule and improve the schedule performance index (SRI).


B.

Implement fast-tracking to compress the schedule and improve the SPI


C.

Perform conflict management using the project's resource management plan.


D.

Review the risk management plan to evaluate the probability and impact of these delays


Expert Solution
Questions # 184:

An integrated project involves the interaction of both hardware and software and the sponsor has approved the schedule management plan The project team evaluated the product's feasibility of functionality and accelerated testing What should the project manager do as a servant leader?

Options:

A.

Support the team as necessary to find the minimum viable product (MVP).


B.

Amend the project budget to include MVP testing


C.

Submit a change request to the project sponsor for accelerated testing.


D.

Develop the product as per the schedule to perform integration and testing


Expert Solution
Questions # 185:

Which two actions should a project manager consider while launching a new virtual team? (Choose two)

Options:

A.

Recruit the best resources within the organization to be part of the virtual team


B.

Evaluate the project manager’s own strengths and weaknesses as a virtual team leader to identify avoidable pitfalls


C.

Identify the types and quantities of resources required for each work package or activity


D.

Establish in the beginning, how progress will be monitored and the best means for communicating progress


E.

Verify if team members are on more than one team and cannot devote enough time to this team


Expert Solution
Questions # 186:

An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)

Options:

A.

Ask the stakeholders about the priority of this change


B.

Ask the product owner to review the product backlog


C.

Ask the team members to analyze the impact of this change


D.

Ask the sponsor to approve the change request


E.

Ask the team members to include the change in the next iteration


Expert Solution
Questions # 187:

A project manager is managing an innovation project for a big corporation The project manager is planning to use email as the main communication channel, however, the product owner prefers to use another approved communication tool instead of email

What should the project manager do?

Options:

A.

Contact the sponsor to request direction regarding the communication tool to be used by the project team


B.

Update the communications management plan based on the product owner’s

preferences and distribute to the team


C.

Suggest to the team to start using the communication tool suggested by the product owner


D.

Request the product owner to use email because using another tool will increase the workload


Expert Solution
Questions # 188:

Due to delays on some activities one of the project team members has increased the scope without any approval What should the project manager do next?

Options:

A.

Remove the changes to match the original requirements.


B.

Add team members to the project to avoid more schedule delays.


C.

Evaluate the impacts of the changes that were made to the project


D.

Update project documentation with the new scope


Expert Solution
Questions # 189:

How should the project manager develop the project management plan to ensure that the project continually delivers the expected benefits?

Options:

A.

Clarify project benefits with the sponsor.


B.

Identify the goal of each work product


C.

Perform integration testing of each release


D.

Include the entire project team in testing


Expert Solution
Questions # 190:

During the last sprint review, the mam stakeholder complained that the product was missing many features they had been expecting The project team argued that every increment met the acceptance criteria and was approved by the mam stakeholder The cost performance index (CPI) of the project is 1 15 and the schedule performance index (SPI) is 1.43

What should the project manager do?

Options:

A.

Ask the project team to perform the modifications since the project budget and schedule can support them.


B.

Ask the stakeholder to submit a change request to increase the budget and time for the modifications requested


C.

Explain to the stakeholder that since the acceptance criteria for every increment were met the project can be closed.


D.

Analyze the reason for the gap in understanding with both sides and negotiate a solution


Expert Solution
Questions # 191:

A new project manager is assigned to a project midway through its implementation During the first risk review meeting, the project manager notices that the version of the risk register used by the project team members is different from the one the project manager is using

What should the project manager have done to avoid this issue?

Options:

A.

Referred to the communications management plan


B.

Validated the issue log


C.

Validated the project artifacts


D.

Performed expert judgment


Expert Solution
Questions # 192:

During the course of the project several obstacles are identified that are preventing the project from moving forward. What should the project manager do to remove the obstacles?

Options:

A.

Have the project team work on other activities


B.

Implement plans to remove the obstacles


C.

Escalate to the project steering committee


D.

Prioritize the obstacles for resolution


Expert Solution
Questions # 193:

An organization has historically executed most projects using a predictive approach The organization now wants to change over to an agile approach

Which strategy will be useful to effectively help prepare the organization for this change?

Options:

A.

Create a task force of executives who will monitor agile projects on a daily basis


B.

Add multiple layers of managers who will be accountable for the agile execution


C.

Improve organizational readiness by addressing impediments to agile in the organization.


D.

Take a big bang approach of moving the whole organization to agile at once


Expert Solution
Questions # 194:

A marketing team is developing ideas in order to revamp an existing product The marketing executive reaches out to the project manager to make sure that necessary measures are in place for a successful launch

On what should the project manager focus?

Options:

A.

Ensuring that the team is also focused on the overall change management plan


B.

Determining and aligning performance indicators that will help in assessing successful delivery


C.

Planning for regular project updates to cover the status of critical deliverables


D.

Ensuring that the scope management plan is in place to cover all related objectives


Expert Solution
Questions # 195:

A project manager who is new to a matrix organization has just been assigned to an internal software development project that is intended to

reduce conflicts in the company’s internal tracking system. With over 1,000 people in the company who will benefit from the software, the project

manager wants to ensure everyone is aware of the great progress the team is making. The project manager meets with the project team to decide

upon the most effective way to communicate progress.

What should the project manager do?

Options:

A.

Send weekly emails to each stakeholder providing them with the project's progress.


B.

Ask the project sponsor to disseminate project progress across the organization's stakeholders.


C.

Set up an intranet site and allow stakeholders to access the relevant project information.


D.

Divide up the organization among the project team to provide direct project updates.


Expert Solution
Questions # 196:

A Scrum team is analyzing the burndown chart on day four of a 15-day sprint. The burndown chart is shown below. What should the team do next?

Question # 196

Options:

A.

Ask the product owner if some low-priority stories could be cut from the sprint.


B.

Continue with the sprint as the progress shows buffers for potential interruptions.


C.

Ask the project team to select any additional stories as they have additional capacity than planned.


D.

Continue with the sprint work as planned and keep monitoring.


Expert Solution
Questions # 197:

During a project status meeting with senior managers, the project manager gives an update about the status of a deliverable. Some of the senior managers claim not to Know about the deliverable.

What should the project manager do next?

Options:

A.

Validate if the project charter changed from the original one.


B.

Meet with these stakeholders to review the project charter.


C.

Check if these stakeholders attend regular project meetings.


D.

Review the project charter to validate this claim.


Expert Solution
Questions # 198:

A software delivery project began having technical impediments. The issue may cause a delay of the deliverables. The technical service team has been working on the issue, but the issue is unresolved even after 1 week of maintenance.

What should the senior project manager do now?

Options:

A.

Use interpersonal skills to expedite the issue.


B.

Send a gentle reminder to the technical service team.


C.

Update the issue log with the status and priority.


D.

Issue a formal warning to the technical service team.


Expert Solution
Questions # 199:

An agile project team received an assignment to develop an industrial system that interfaces with robots. The project team does not have any previous experience

performing this type of work. Team members are interested in acquiring such expertise but it may result in a project delay.

How should this situation be handled?

Options:

A.

Use a robotics vendor company to develop the interfaces so the team will not be held back by a lack of expertise in this type of work,


B.

Add an experienced professional to the team to reinforce knowledge sharing and help grow team expertise in the new product


C.

Create a separate team with experienced members who understand the technology and split the product backlog according to team specialization.


D.

Hire a consulting company to address the robotic interface questions, when necessary, and to help avoid delays and quality issues.


Expert Solution
Questions # 200:

A project was initiated due to an external business influence. During the course of the project, some of the business parameters considered at the

beginning of the project have changed.

What should the project manager do?

Options:

A.

Inform the team not to accept any changes, as it involves significant rework.


B.

Request management to update the project requirements accordingly.


C.

Request an update of only new requirements, as other changes involve rework.


D.

Inform management that the agreed-upon scope cannot be changed.


Expert Solution
Viewing page 4 out of 12 pages
Viewing questions 151-200 out of questions