PMI Project Management Professional (2025 Version) PMP Question # 174 Topic 18 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 174 Topic 18 Discussion

PMP Exam Topic 18 Question 174 Discussion:
Question #: 174
Topic #: 18

A project manager is quantifying risk for their project. The project manager needs an expert opinion in this process, but experts are spread over different geographic locations and time zones.

What should the project manager do?


A.

Apply the critical path method (CPM).


B.

Use the Delphi Technique.


C.

Use the Monte Carlo analysis online.


D.

Utilize story point estimating.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.