PMI Project Management Professional (2025 Version) PMP Question # 174 Topic 18 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 174 Topic 18 Discussion

PMP Exam Topic 18 Question 174 Discussion:
Question #: 174
Topic #: 18

An agile project is in its eighth iteration out of 16 After the last iteration review, the team members receive feedback from the security department about regulations with which the project must comply

Which two actions should the project manager take? (Choose two)


A.

Ask the team members to analyze the impact of including this regulation


B.

Ask the stakeholders about the priority of this regulation


C.

Ask the product owner to include the requirements in the product backlog


D.

Ask the security department for details about regulations


E.

Ask the team members to include the requirements in the next iteration


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.