New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 173 Topic 18 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 173 Topic 18 Discussion

PMP Exam Topic 18 Question 173 Discussion:
Question #: 173
Topic #: 18

A multimillion-dollar project has started and is in the execution phase. A local regulatory authority has just announced changes to the requirements that will need to be implemented in 6 months, prior to completing the project execution phase.

What should the project manager do next?


A.

Add the new requirements to the project scope immediately since they are mandatory changes.


B.

Review the new requirements with the compliance department to determine if a change request is needed.


C.

Ignore the new requirements as the current budget and schedule do not allow for any changes.


D.

Proceed with the defined project requirements and delay implementing the new requirements.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.