PMI Project Management Professional (2025 Version) PMP Question # 173 Topic 18 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 173 Topic 18 Discussion

PMP Exam Topic 18 Question 173 Discussion:
Question #: 173
Topic #: 18

The project team finds that the latest delivery from a vendor is missing a critical component, which will likely delay the project in split of corrective measures. What should the project manager do to communicate this message?


A.

Ask the vendor to identify the stakeholders affected, create an action plan and determine an implementation date


B.

Draft a warning letter to the vendor ask internal stakeholders to comment, and solicit stakeholder support to hold the vendor accountable


C.

Identify the worst-case scenario, put it into the project risk register, share the register with all project stakeholders, and raise an alert.


D.

Contact department managers who are identified as stakeholders, solicit concern, and provide updates to the situation