PMI Project Management Professional (2025 Version) PMP Question # 173 Topic 18 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 173 Topic 18 Discussion

PMP Exam Topic 18 Question 173 Discussion:
Question #: 173
Topic #: 18

A project is ready to deliver the first batch of the product when a quality control check rejects the product as unfit for delivery. The root cause

analysis (RCA) shows that a component added as part of the latest change request was not tested throughout the development cycle.

What should the project manager do next?


A.

Review the change control process to ensure quality management artifacts are updated as part of the change.


B.

Review the quality management process and perform a process audit as part of ongoing quality assurance.


C.

Review the communications management plan to ensure change requests are communicated to the affected team members.


D.

Review the quality management process with the project management office (PMO) to ensure compliance with best practices.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.