PMP Exam Topic 16 Question 151 Discussion:
Question #: 151
Topic #: 16

A project has obtained all of the necessary legal requirements and policies from the local government. During the execution phase, the product owner is informed that a new law impacting the project deliverables will be published within two weeks.

What should the project lead do?


A.

Review the product backlog items to evaluate the impact on scope and prioritize accordingly.


B.

Develop a change request for more resources and update the project budget and schedule.


C.

Ask the internal legal department to evaluate if the regulatory law could be managed internally.


D.

Work with the team to develop an alternative solution with no additional effect on the project's budget.