PMI Project Management Professional (2025 Version) PMP Question # 144 Topic 15 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 144 Topic 15 Discussion

PMP Exam Topic 15 Question 144 Discussion:
Question #: 144
Topic #: 15

A team member on an important company project mistakenly caused significant cost overruns. The sponsor informed the project manager and expects the project manager to take action within 1 week. This team member has always been an outstanding performer.

What should the project manager do first to address the sponsor's concerns?


A.

Document the team member's mistake in the lessons learned.


B.

Train the team member to improve their performance to avoid future mistakes.


C.

Talk with the team member to identify the reason for the mistake.


D.

Relocate the team member to another project due to the mistake.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.