New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 144 Topic 15 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 144 Topic 15 Discussion

PMP Exam Topic 15 Question 144 Discussion:
Question #: 144
Topic #: 15

How can agile measurements improve upon predictive measurements in cases where the final 10% of a project takes longer than planned?


A.

By scheduling iterative meetings with the product owner to improve project tracking


B.

By focusing on the delivery of incremental working products lo the customer


C.

By reviewing burnup charts to determine the effort required against estimated earned value


D.

By conducting daily standups to more accurately track project deliverables


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.