PMI Project Management Professional (2025 Version) PMP Question # 144 Topic 15 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 144 Topic 15 Discussion

PMP Exam Topic 15 Question 144 Discussion:
Question #: 144
Topic #: 15

The project team follows a hybrid framework for its delivery. During the execution of a project, the team learns of a new compliance requirement that has to be delivered before any other requirements

How should the project manager address this situation?


A.

Ask the team to include the compliance requirement in the current sprint and deliver it.


B.

Add the new compliance requirement to the backlog as the technical team does not have any capacity.


C.

Include the compliance lead in the stakeholders list and wait for the next status meeting


D.

Collaborate with the compliance team member to review and prioritize the requirement’s delivery


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.