PMI Project Management Professional (2025 Version) PMP Question # 147 Topic 15 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 147 Topic 15 Discussion

PMP Exam Topic 15 Question 147 Discussion:
Question #: 147
Topic #: 15

A project manager regularly sends out project progress reports. However, there have been a few complaints from stakeholders who expressed that the communication does not meet their needs.

What should the project manager do?


A.

Analyze the communication needs of the stakeholders.


B.

Communicate the project details to the stakeholders.


C.

Communicate progress more frequently to the stakeholders.


D.

Introduce a separate stakeholder engagement meeting.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.