Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 59 Topic 6 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 59 Topic 6 Discussion

PMP Exam Topic 6 Question 59 Discussion:
Question #: 59
Topic #: 6

Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?


A.

Evaluate the impact of skipping the quality check for the deliverable.


B.

Seek approval from the sponsor on an extension of the project schedule,


C.

Seek approval from the quality board to skip the quality check.


D.

Ask the team member to work overtime to complete the quality check.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.