PMP Exam Topic 6 Question 59 Discussion:
Question #: 59
Topic #: 6

A project manager is assigned to a project where a vendor has been engaged to build a new system One week before user acceptance testing (UAT) is scheduled the vendor informs the project manager that they can only deliver half of the promised functions by the UAT start date.

What should the project manager do next?


A.

Wait until the vendor cannot deliver and then invoke liquidated damages based on the contract


B.

Escalate to management and prepare tor project closure by canceling the contract with this vendor


C.

Adjust the protect schedule to accommodate the current development progress of the vendor


D.

Communicate with the vendor and project team and explore possibilities lor resolving the issue