New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 59 Topic 6 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 59 Topic 6 Discussion

PMP Exam Topic 6 Question 59 Discussion:
Question #: 59
Topic #: 6

A project manager is leading a software development team to upgrade a banking software. During a sprint review, the product owner suggested a small addition to the process that might necessitate a change to the sprint.

What should the project manager do?


A.

Review the proposed change with the team and consult the project sponsor for approval.


B.

Evaluate the product owner's proposed change alone and consult the project sponsor for approval.


C.

Submit the proposed change to the change control board (CCB) to evaluate and approve.


D.

Accept the product owner's suggested change and notify the project sponsor of the acceptance.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.