PMI Project Management Professional (2025 Version) PMP Question # 152 Topic 16 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 152 Topic 16 Discussion

PMP Exam Topic 16 Question 152 Discussion:
Question #: 152
Topic #: 16

A learn has been working for two months and has consistently missed planned user stories How should the project manager address this issue?


A.

Ensure the sprint size is appropriate for the iteration duration.


B.

Promote changing the iteration duration in order to commit as planned.


C.

Engage in recruiting a highly skilled resource to reinforce the skills.


D.

Consider using a reward system to encourage timely delivery


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.