PMI Project Management Professional (2025 Version) PMP Question # 152 Topic 16 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 152 Topic 16 Discussion

PMP Exam Topic 16 Question 152 Discussion:
Question #: 152
Topic #: 16

A project team is working together for the first time. During the first sprint, the project manager was asked to solve a prioritization conflict between the Scrum Master and the Product Owner related to a feature requested by an important customer.

How should the project manager resolve this conflict?


A.

Refer to the roles and responsibilities for the agile team.


B.

Schedule a meeting with the Scrum Master and Product Owner.


C.

Emphasize that the Scrum Master has the responsibility to conduct the sprint planning.


D.

Contact the customer to understand the request in order to make a decision.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.