PMP Exam Topic 16 Question 156 Discussion:
Question #: 156
Topic #: 16

A team is using an agile approach to maintain the project backlog. A new project obstacle was identified as a blocker and added to the backlog list. The team is facing challenges to remove this obstacle.

What should the project manager do next?


A.

Escalate the obstacle to a servant leader for resolution.


B.

Make changes to reprioritize the backlog because of the obstacle.


C.

Reject the obstacle and present the partial solution to the customer.


D.

Focus on generating business value despite the obstacle.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.