Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 154 Topic 16 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 154 Topic 16 Discussion

PMP Exam Topic 16 Question 154 Discussion:
Question #: 154
Topic #: 16

A company's CEO complains about the frequency of project communications. The CEO receives five project reports each week by email but does not have enough time to review them. In addition, the information that the CEO receives is not relevant in that it does not explain the project status,

What should the project manager do first?


A.

Review the stakeholder engagement plan.


B.

Review the communications management plan.


C.

Send the CEO one executive summary per week instead of five reports per week.


D.

Meet with the team and decide the type and frequency of the reports to send to the CEO.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.