PMI Project Management Professional (2025 Version) PMP Question # 154 Topic 16 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 154 Topic 16 Discussion

PMP Exam Topic 16 Question 154 Discussion:
Question #: 154
Topic #: 16

A group has been working together for one month. During daily meetings a team member continues to express issues in completing their tasks.

What should the project manager do?


A.

Wait for the team to identify and solve the problem independently.


B.

Move the team member to another task that is more skill appropriate


C.

Have a confidential discussion with the team member to identify the root cause


D.

Start a discussion with all team members to help resolve the issues


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.