PMI Project Management Professional (2025 Version) PMP Question # 161 Topic 17 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 161 Topic 17 Discussion

PMP Exam Topic 17 Question 161 Discussion:
Question #: 161
Topic #: 17

A project is delivered using a hybrid approach. In the daily meeting, one of the developers informs the team that the business that will implement the next version of the product has a new manager. There is one more sprint before the new version of the product enters the staging phase.

What should the project manager do?


A.

Invite the new manager to the next daily scrum.


B.

Invite the new manager to the next sprint review.


C.

Invite the new manager to the next sprint planning.


D.

Invite the new manager to the next sprint retrospective.