New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 148 Topic 15 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 148 Topic 15 Discussion

PMP Exam Topic 15 Question 148 Discussion:
Question #: 148
Topic #: 15

A project manager is assigned to a major construction project. The project is critical to the city's population, and especially to the local government

official who committed to delivering the project on time as an election promise. A new project sponsor has been assigned and wants to include

aspects that the previous project sponsor did not support.

What should the project manager do next?


A.

Meet with the new project sponsor to review the current project scope and the requested changes.


B.

Rebaseline the project as there is now a new project sponsor, which is presenting an opportunity to review and recalibrate the project objectives.


C.

Invite the project sponsor to a briefing with the project team to demonstrate progress and seek further support to meet project-committed deliverables.


D.

Inform the new project sponsor that the new aspects will not be included in this project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.