PMI Project Management Professional (2025 Version) PMP Question # 148 Topic 15 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 148 Topic 15 Discussion

PMP Exam Topic 15 Question 148 Discussion:
Question #: 148
Topic #: 15

A government approved the construction of a river dam to enable year-round farming in a community. At the project kickoff meeting, a key stakeholder in the community disagrees with the location of the dam.

What should the project manager do first?


A.

Review the stakeholder engagement plan to confirm that all key stakeholders were consulted.


B.

Explain to the key stakeholder that final approval has already been obtained.


C.

Meet with the key stakeholder to review the stakeholder engagement plan.


D.

Schedule a meeting with all stakeholders to discuss the view of this key stakeholder.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.