PMI Project Management Professional (2025 Version) PMP Question # 148 Topic 15 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 148 Topic 15 Discussion

PMP Exam Topic 15 Question 148 Discussion:
Question #: 148
Topic #: 15

The team is working on a critical project deliverable and the project manager is concerned about meeting the deadline There have been complaints from some stakeholders about some of the team members' performance The project manager wants to understand the situation and provide feedback to the team as soon as possible

What three actions should the project manager take to address this situation? (Choose three)


A.

Define team ground rules


B.

Perform a retrospective session


C.

Implement daily team meetings.


D.

Request a manager performance review


E.

Conduct an annual review.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.