Question #: 620
Topic #: 63

A project manager is leading a project with a predictive approach for a governmental body with strictly defined requirements. In the middle of the project, the sponsor requires a significant new feature to be included. This feature was not in the original plan, nor was it part of the planning process,

What should the project manager do?


A.

Descope low-priority features that were not explicitly requested and add this feature as a high priority.


B.

Inform the senior manager that they will need a new project management plan for this feature,


C.

Complete the most current feature and release the resources for the new feature.


D.

Analyze the impact of this change and present the options to the senior manager.