Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 162 Topic 17 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 162 Topic 17 Discussion

PMP Exam Topic 17 Question 162 Discussion:
Question #: 162
Topic #: 17

A project manager noticed that the functional manager is not cooperating with staff assignment schedules and is always finding excuses not to release the requested staff. What should the project manager do first?


A.

Ask the leadership team for help obtaining the needed staff.


B.

Have a direct talk with the functional manager to understand the reasons behind their attitude.


C.

Evaluate the impact caused by the delay of forming the team and confront the functional manager.


D.

Check with human resources (HR) regarding the availability of staff.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.