A research and development team is finishing up a two year initiative The project manager is focused on the closing activities for the project.

Which activity should be considered as a priority?


A.

Mark the product backlog completion status and update the communications management plan.


B.

Ensure that knowledge transfer activities are executed as planned


C.

Release the resources and plan for a project completion celebration.


D.

Hold a steering committee meeting to inform them of the project completion