PMI Project Management Professional (2025 Version) PMP Question # 153 Topic 16 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 153 Topic 16 Discussion

PMP Exam Topic 16 Question 153 Discussion:
Question #: 153
Topic #: 16

A project manager is leading a software development project. At the start of the project, the project team decides that iterations are the best way to run the project and deliver value to the customer more quickly.

Which three actions should the project manager take? (Choose 3)


A.

Develop the project management plan based on the requirements requested by the customer.


B.

Develop the application as requested by the customer, based on the approved project requirements.


C.

Plan a minimum viable product (MVP) to get early feedback from the customer.


D.

Facilitate a focus group to assess the functionality before development.


E.

Use an agile approach to deliver the product based on sprints.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.