New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 198 Topic 20 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 198 Topic 20 Discussion

PMP Exam Topic 20 Question 198 Discussion:
Question #: 198
Topic #: 20

A product owner has returned from a meeting with a few key stakeholders, who expressed interest in learning more about the project progress. The product owner is

seeking the project manager's recommendation on how to approach this request.

What should the project manager do to help the product owner?


A.

Provide an overview of the completed functionalities and release plan, and capture expectations for future stakeholder involvement.


B.

Invite the product owner to future demonstrations where they can provide feedback.


C.

Provide access to the latest user acceptance test (UAT) environment so they can see the solution.


D.

Remind the product owner of stakeholder accountability, and ask the product owner to determine the appropriate next steps.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.