Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 53 Topic 6 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 53 Topic 6 Discussion

PMP Exam Topic 6 Question 53 Discussion:
Question #: 53
Topic #: 6

A project manager was replaced in the early phases of a new project. The new project manager discovers that the business team is not supporting the project. After

discussing these concerns with the team, it is determined that the project does not have the full support of senior management.

What should the new project manager do next?


A.

Send out a status report describing the situation to the stakeholders and request general assistance.


B.

Request the business team to clearly define their issues with the project work completed to date.


C.

Study the stakeholder analysis to understand which stakeholder holds the most influence and seek their assistance.


D.

Ask senior management to be more involved with the project and to provide their full support.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.