PMI Project Management Professional (2025 Version) PMP Question # 53 Topic 6 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 53 Topic 6 Discussion

PMP Exam Topic 6 Question 53 Discussion:
Question #: 53
Topic #: 6

A company is launching a new product and decides to transition from a predictive to an agile approach. During the third sprint the project manager notices that the team is not working as a cohesive unit

Which two rules are appropriate tor the project manager to instill in the team? (Choose two)


A.

Strive toward continuous improvement


B.

Work together daily as a team


C.

Only share suggestions at the end of the sprint


D.

Follow the sprint planning


E.

Send communications to the entire team


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.