Comprehensive and Detailed Explanation:
At the close of a project, especially one involving multiple agile streams, the best practice is to conduct a formal lessons learned session (also known as a retrospective or post-mortem). This allows comprehensive collection of what went well, what didn’t, and how to improve future projects.
* B is limited to only one sprint.
* C is not the appropriate forum for final reflections.
* D may provide leadership insights but not team-level experience.
[References:, , * PMBOK® Guide – Seventh Edition, Performance Domain: Measurement and Closing, * Agile Practice Guide, Section on Retrospectives and Continuous Improvement, , ──────────────────────────────────────────────, Here are the verified answers with detailed explanations for PMP questions 1831 to 1834, presented in the required format., , ──────────────────────────────────────────────, , ]