Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 52 Topic 6 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 52 Topic 6 Discussion

PMP Exam Topic 6 Question 52 Discussion:
Question #: 52
Topic #: 6

‘An organization undergoes a major budget revisal. The project manager gathers the stakeholders to discuss the situation as some projects are stil in-progress and may be impacted.

What two actions should the project manager take? (Choose 2)


A.

Update the risk register and plan new response strategies.


B.

Conduct a risk reassessment and quantify mitigating measures.


C.

Request the stakeholders to fill any gap in the budget.


D.

Adjust the project ' s risk thresholds to support budget changes.


E.

0 Ask stakeholders to discuss terminating the running projects.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.