PMI Project Management Professional (2025 Version) PMP Question # 52 Topic 6 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 52 Topic 6 Discussion

PMP Exam Topic 6 Question 52 Discussion:
Question #: 52
Topic #: 6

A company was acquired, and the new company management asked the project manager to begin using a specific set of metrics immediately to measure team performance. The project manager is working on a predictive project and thinks this request will distract the team and delay the project.

What should the project manager do first?


A.

Assess and analyze the impact of using these metrics.


B.

Involve the team in reviewing the proposed metrics.


C.

Request an extension to implement the new metrics.


D.

Support the required metrics during the next project phase.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.