PMI Project Management Professional (PMBOK 7th Version) PMP Question # 52 Topic 6 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 52 Topic 6 Discussion

PMP Exam Topic 6 Question 52 Discussion:
Question #: 52
Topic #: 6

During a project gate review meeting, it is identified that one of the project

deliverables will require corrective actions to meet the project quality requirements. What

should the project manager do first?


A.

Update the risk register and implement the approved risk response plan for qualitydeviations.


B.

Identify the resources that were responsible for the deliverable and request a teamdevelopment plan.


C.

Update the issue log, identify the involved stakeholders, and assign resources to thecorrective actions.


D.

Submit a change request to update the project quality requirements for the involvedproject deliverable.