New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 50 Topic 6 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 50 Topic 6 Discussion

PMP Exam Topic 6 Question 50 Discussion:
Question #: 50
Topic #: 6

A project sponsor indicates that the time frame for a project needs to be shortened. The project network diagram cannot be modified, but there are extra resources available in the company.

What action should the project manager take?


A.

Crash the project schedule.


B.

Conduct earned value management (EVM) analysis.


C.

Fast track the project.


D.

Perform Monte Carlo analysis.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.