PMI Project Management Professional (2025 Version) PMP Question # 50 Topic 6 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 50 Topic 6 Discussion

PMP Exam Topic 6 Question 50 Discussion:
Question #: 50
Topic #: 6

Anew systems project requires feedback from the accounting manager at the beginning of solution discussions and before meeting with other functional managers. The project manager knows the accounting manager will not be available until a few days before the deadline for the solution

document.

What should the project manager do to avoid a delay in the project?


A.

Ask the accounting manager to delegate a team member who can support the project.


B.

Wait for the accounting manager to be available while identifying subsequent tasks that can be compressed,


C.

Request that the sponsor direct the accounting manager's supervisor to provide a replacement resource,


D.

Begin discussions with other functional managers and meet with the accounting manager later.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.