PMI Project Management Professional (2025 Version) PMP Question # 49 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 49 Topic 5 Discussion

PMP Exam Topic 5 Question 49 Discussion:
Question #: 49
Topic #: 5

A client from the travel and hospitality industry is building software for an ongoing project. The project sponsor and key project stakeholders ask to add four new functionalities to the upcoming sprint.

What should the product owner do next?


A.

Ask the team to start implementing the new tasks.


B.

Add the new tasks to the current sprint backlog.


C.

Request a change control to expand the scope with the new tasks.


D.

Prioritize the new tasks in the planning of the upcoming sprint.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.