PMI Project Management Professional (2025 Version) PMP Question # 49 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 49 Topic 5 Discussion

PMP Exam Topic 5 Question 49 Discussion:
Question #: 49
Topic #: 5

A company initiated a departmental transformation project improving the processes for the organization using a predictive approach, This is a critical project for the organization and, in the middle of the project, the project manager noticed that one of the deliverables cannot be produced due to a missing technical skill.

What should the project manager have done to avoid this?


A.

Planned all required training for the team during the onboarding process


B.

Identified all required skills after the kick-off of the project


C.

Identified all required skills during the planning of the project


D.

Asked the sponsor to identify all required skills during the planning of the project


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.