PMP Exam Topic 5 Question 49 Discussion:
Question #: 49
Topic #: 5

An updated schedule for work delivered by a subcontractor is a condition for a milestone payment. The subcontractor completed the work but does not have a schedule, claiming that work was already agreed upon with the client.

What should the project manager do?


A.

Negotiate a contract change with the subcontractor.


B.

Meet with the client to discuss the issue with the subcontractor.


C.

Inform the subcontractor that they must send the schedule.


D.

Tell the subcontractor to submit a draft schedule.