New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 49 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 49 Topic 5 Discussion

PMP Exam Topic 5 Question 49 Discussion:
Question #: 49
Topic #: 5

The project sponsor wants to obtain quick feedback from end users for a product under development. The roadmap is extensive and will not be completed for quite some time.

What should the project manager do?


A.

Advise the stakeholders that they will need to wait until development is completed in order to get actual end-user feedback.


B.

Hire additional resources to accelerate the schedule and deliver the product faster in order to get actual end-user feedback.


C.

Advise the stakeholders to share images of the finished product in order to obtain valuable feedback from end users.


D.

Work with the stakeholders to determine the minimum requirements needed to get valuable end-user feedback and revise the project schedule.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.