Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 49 Topic 5 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 49 Topic 5 Discussion

PMP Exam Topic 5 Question 49 Discussion:
Question #: 49
Topic #: 5

During a project status meeting, two project stakeholders disagree about what should be included in the next deliverable. One of the stakeholders would like the team to include a finalized version of the new component in the release. Using the finalized version will impact the project timeline. The second stakeholder would like the team to include a beta version of the new component to allow the client to provide feedback before the component is finalized.

What should the project manager do next?


A.

Implement the beta version of the component because it will not impact the project timeline.


B.

Mediate the disagreement by scheduling a meeting to agree on a solution.


C.

Implement the finalized version of the component because it will impact the project timeline.


D.

Choose the inclusion that will result in the least amount of risk.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.