Question #: 197
Topic #: 20

A project manager is assigned to a regulatory project for their country. The deadline for delivering results in compliance with the new laws is very tight, and the project team members have not yet been assigned. One of the project manager's peers informs the project manager that a project with the same scope for a different country was completed 1 year ago.

What should the project manager do first?


A.

Register a new risk in the risk management plan.


B.

Ask for additional resources and review the project estimate.


C.

Review organizational process assets (OPAs) and perform analogous estimating.


D.

Complete a bottom-up estimation for the project activities.