Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 197 Topic 20 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 197 Topic 20 Discussion

PMP Exam Topic 20 Question 197 Discussion:
Question #: 197
Topic #: 20

A telecommunications company is doing a national network rollout involving continuously changing technical requirements. To address the situation the company has recently adopted a hybrid project life cycle. During a retrospective some team members complain that me majority of me stones are ready to test but have not advanced because they are waiting for the project manager's approval.

What should the project manager do?


A.

Update the issue log and review the lessons learned register for options


B.

Implement conflict resolution to accommodate the team's needs


C.

Implement decision-making techniques to advance the stones


D.

Empower the team to self-organize and make their own decisions


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.