PMI Project Management Professional (2025 Version) PMP Question # 197 Topic 20 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 197 Topic 20 Discussion

PMP Exam Topic 20 Question 197 Discussion:
Question #: 197
Topic #: 20

A project manager is managing a project with a hybrid approach and has requested a senior team member to perform a quantitative risk analysis The team member responds that they do not have the knowledge to perform such an analysis.

What should the project manager do?


A.

Contact the project management office (PMO) and request them to assign another team member who has the knowledge to perform this task to the team


B.

Escalate the issue to the functional manager


C.

Help the team member to perform the quantitative risk analysis through coaching, mentoring and training


D.

Perform the quantitative risk analysis for the team member.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.