Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 194 Topic 20 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 194 Topic 20 Discussion

PMP Exam Topic 20 Question 194 Discussion:
Question #: 194
Topic #: 20

A project manager has been assigned to a project where the budget is very tight. Incurring extra costs is not an option.

What should the project manager do to manage this situation?


A.

File a change request to make the customer billable for all extra costs incurred for the project.


B.

Ask the accounting department to forward all project expenses to the project manager's email.


C.

Monitor the budget for the project continually and anticipate any issues if possible.


D.

Ask the project resources to finish their assignments in less time than originally planned.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.