Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 194 Topic 20 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 194 Topic 20 Discussion

PMP Exam Topic 20 Question 194 Discussion:
Question #: 194
Topic #: 20

A team has developed and tested new software to control airplanes during flights. There are several regulatory requirements that must be met. What should the project manager do to meet these requirements?


A.

Determine potential threats regarding compliance with the regulations.


B.

Ask human resources (HR) to assign a compliance specialist to the team.


C.

Validate that the software is compliant with standards and regulations.


D.

Measure the extent to which the project complies with the regulations.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.