Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 199 Topic 20 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 199 Topic 20 Discussion

PMP Exam Topic 20 Question 199 Discussion:
Question #: 199
Topic #: 20

A customer has provided excellent feedback on the project. However, a key project resource is leaving the company.

Which measure should mitigate the impact of this key resource's departure?


A.

Offer a new contract to the resource who is leaving.


B.

Establish a proactive knowledge-sharing plan.


C.

Update the risk register and inform the customer.


D.

Develop a contingency budget to replace the key resource.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.