PMP Exam Topic 21 Question 200 Discussion:
Question #: 200
Topic #: 21

An organization is using a hybrid delivery approach for a business project. The product owner, the person who was also managing the project, was promoted to a more senior role. A new project lead has joined the project.

Which artifact should the project lead use to ensure that the project benefits have been identified?


A.

Solution architecture


B.

Product backlog


C.

Statement of work (SOW)


D.

Business case