PMI Project Management Professional (2025 Version) PMP Question # 200 Topic 21 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 200 Topic 21 Discussion

PMP Exam Topic 21 Question 200 Discussion:
Question #: 200
Topic #: 21

At the end of planning a new project, the project manager needs to schedule the

kick-off meeting but is having difficulty finding a common time slot when all necessary

stakeholders can be available onsite. How should the project manager proceed to

schedule the kick-off meeting?


A.

Email all stakeholders with the objectives of the project and ask for feedback.


B.

Wait for a date when all required attendees can be available onsite.


C.

Run separate meetings to accommodate everyone's schedule.


D.

Schedule a virtual meeting so onsite and remote stakeholders can attend at the same time.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.