PMI Project Management Professional (2025 Version) PMP Question # 170 Topic 18 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 170 Topic 18 Discussion

PMP Exam Topic 18 Question 170 Discussion:
Question #: 170
Topic #: 18

A project schedule's risk level continues to increase during project execution because sprints are consistently delivering less than the intended results. The project manager becomes concerned that the deliverable will be delayed and cost more than the project sponsor intended.

What should the project manager do first?


A.

Engage with the project team to understand the schedule risk problem and present a solution to the project sponsor.


B.

Conduct a risk review meeting to gain a better understanding of the schedule, then document the results.


C.

Schedule a meeting with the scrum master to explain that adding additional sprints is necessary to reduce risks.


D.

Notify the project sponsor of the schedule risk and request support to increase the project budget.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.