Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 2 out of 12 pages
Viewing questions 51-100 out of questions
Questions # 51:

A few developers have identified a list of impediments at the daily standup and are asking for the project lead's assistance in prioritizing them. There are a few complex backlog items, and a new junior tester has identified a few compliance defects. The product owner and a couple of developers will be leaving the project team, and the contract with the test and production support partner will not be renewed.

Which issue should the project lead focus on first?

Options:

A.

Developing a new contract for production support.


B.

Finding a new product owner to prioritize the product backlog.


C.

Regulatory compliance issues discussed in the meeting.


D.

Recruiting, onboarding, and training new developers.


Expert Solution
Questions # 52:

A development team is struggling to find design documentation for the upcoming sprint. Prior to leaving for vacation, the product owner

communicated that the documentation had been uploaded to the project file repository.

What should the project manager do to address this issue?

Options:

A.

Assign a team member to manage project artifacts.


B.

Audit the effectiveness of the management of project artifacts.


C.

Improve email communication protocols to manage project artifacts.


D.

Investigate new software tools used to manage project artifacts.


Expert Solution
Questions # 53:

A project lead is working on an agile project to build the team's vision, including the decision-making process. It was decided that the team will

vote on items, and if 90% of the team agrees on a decision, then it will be carried forward. At the very first technical design meeting, the team

makes a decision that the project lead strongly disagrees with.

How should the project lead proceed?

Options:

A.

Refuse to let the team proceed with the work based on their decision.


B.

Take the technical team lead aside and try to persuade them to change their vote.


C.

Note the reasons for the disagreement and let the team proceed.


D.

Set up a meeting with the project champion and ask them to intervene.


Expert Solution
Questions # 54:

A key project stakeholder recently joined the project and is questioning some of the previously made decisions. This starts to impact project execution.

What should the project manager do?

Options:

A.

Reach out to the stakeholder via phone to explain that all decisions have been agreed upon with their predecessor.


B.

Provide the stakeholder with a link to a file-sharing site where the supporting documents for decisions are filed.


C.

Schedule a meeting with the stakeholder to provide an overview of the project, including the agreed-upon decisions.


D.

Update the risk register with a new risk of potential project changes as a result of stakeholder misalignment.


Expert Solution
Questions # 55:

In the middle of a software development project, the lead design programmer accepted an offer from a competitor. The project manager needs to find a replacement to meet an upcoming milestone.

What should the project manager do?

Options:

A.

Consult the risk response plan.


B.

Assign the tasks to another team member.


C.

Update the resource calendar.


D.

Issue a request to the change control board (CCB).


Expert Solution
Questions # 56:

As part of planning activities for a new project, the project manager must develop a budget that encompasses the full project scope. What should the project manager do to build the project budget?

Options:

A.

Reference the work breakdown structure (WBS) and project schedule to estimate costs associated with each WBS element.


B.

Schedule a working session with the project sponsor to review the project charter and estimate the cost per project phase.


C.

Review historical project files and lessons learned to identify a similar project and adapt the budget used in the historical project.


D.

Ask key project stakeholders to estimate the cost of delivering the project, then calculate an average that can be used for the budget.


Expert Solution
Questions # 57:

A company's key product is evolving and requires the use of a new technology. No one on the team is familiar with this technology; however, experienced developers on the team volunteered to study the concepts and application and believe they will be able to take full responsibility for the new technology.

What should the project manager do?

Options:

A.

Descope this requirement as the developers have more important tasks.


B.

Support the developers with their intention to learn the new technology.


C.

Hire externally since the internal developers already have assigned work.


D.

Outsource the technology work to a third party so as not to delay work.


Expert Solution
Questions # 58:

A project manager just completed a successful deployment and is preparing to transition the project to an operational state before starting closeout actions. What should the project manager do to ensure that the project is ready to move to an operational state?

Options:

A.

Meet with the project team to review the work breakdown structure (WBS) and confirm deliverables have been delivered.


B.

Develop a plan to repay the technical debt incurred during the project and ensure that the project sponsor agrees with the plan.


C.

Review the project approval requirements in the project charter and confirm who will be approving the project.


D.

Refer to the project’s work in progress (WIP) reports to ensure that there is no additional work in the backlog.


Expert Solution
Questions # 59:

Contract terms used during the tender phase for a new power-generation facility must be revised before signing with the successful bidder because the terms of the tender have been amended to accommodate the new financial regulations on company tax. Which approach should the project manager take to implement this amendment?

Options:

A.

Sign the contract as per the original terms but allow the successful bidder to submit a new contract price.


B.

Amend the contract terms and sign a revised contract with the successful bidder.


C.

Retender the entire scope because the terms of the contract have changed significantly.


D.

Discuss the new terms with the successful bidder to assess its impact on the contract price.


Expert Solution
Questions # 60:

A project manager notices that the project team is encountering product issues while coding client-specific developments. The project manager foresees delays to the project's timeline because of these product issues.

Which methods should the project manager use to communicate project delays and other difficult messages to stakeholders?

Options:

A.

Oral feedback, project meetings, and reporting


B.

Project meetings and reporting


C.

Project meetings and oral feedback


D.

Written feedback, project meetings, and reporting


Expert Solution
Questions # 61:

A large matrix organization is adopting a new communications approach. This is necessary because their projects often require the resourcing of expert knowledge in the form of specialists from various departments and divisions.

What should the project manager do to set up effective communications?

Options:

A.

Plan on transmitting the information in an easily understandable manner.


B.

Focus on the recipients’ needs and not the information itself.


C.

Use the highest possible technical language and avoid using metaphors.


D.

Ensure that messages sent to the recipients are delivered.


Expert Solution
Questions # 62:

An agile project has a broad set of product features intended for different user profiles and usages. It is difficult to define common acceptance criteria that can apply to all the features.

How can the project manager ensure that the appropriate acceptance criteria are applied to the features?

Options:

A.

Define the acceptance criteria and specific functional test cases only after analyzing the user feedback from testing the early feature release.


B.

Integrate the acceptance criteria review into the definition of ready (DoR) for each feature and associated tests into the feature's definition of done (DoD).


C.

Use the broadest set of acceptance criteria to ensure that all features have a common quality baseline and associated functional test cases.


D.

Integrate the specific tests into the definition of ready (DoR) for each feature and the acceptance criteria into the feature's definition of done (DoD).


Expert Solution
Questions # 63:

During the testing phase of a project, the project manager is made aware that components delivered from a specific vendor have defects. However, the vendor refuses to fix the defects because it will incur additional costs for them.

What should the project manager do next?

Options:

A.

Ask the vendor for revised timelines and cost needs.


B.

Review the acceptance criteria defined with the vendor.


C.

Communicate with the vendor for contract changes.


D.

Request cancellation of the contract with the vendor.


Expert Solution
Questions # 64:

A key stakeholder who is highly involved in the project claims that the reports sent by the project team are inadequate. What should the project manager do first?

Options:

A.

Ask the project team to review and modify all of these reports.


B.

Ask the sponsor to meet with the stakeholder to diffuse the situation with the reports.


C.

Explain to the stakeholder that these are the approved templates for the reports.


D.

Ensure that the reports comply with the communications management plan.


Expert Solution
Questions # 65:

After the first iteration, a scrum master notices that some of the team members are struggling with testing their developed product. What should the scrum master do next?

Options:

A.

Log the issue and see if improvements show in the second iteration.


B.

Log the issue and ask a senior member to coach these team members.


C.

Hire new team members to implement the correct way of testing.


D.

Check lessons learned and use the testing process from previous projects.


Expert Solution
Questions # 66:

A project team has installed software for the client, passed the knowledge to operations, sent the final report, and celebrated. Then 1 week later,

the client sendsa list of requirements that have not been met. The client is requesting to fix the issues quickly and within the initial budget.

What should the project manager have done to prevent this from happening?

Options:

A.

Reviewed the acceptance criteria and obtained client approval.


B.

Allocated a risk budget for any post-release improvements.


C.

Conducted a pilot to understand the client's performance parameters.


D.

Established meetings with the client throughout the project phases.


Expert Solution
Questions # 67:

A company is going through a large cost-cutting initiative. Senior management requests a report on the work remaining for outstanding projects.

Which tool should the project manager use for this purpose?

Options:

A.

Cumulative flow diagram


B.

Earned value (EV)


C.

Burndown chart


D.

Forecast estimation


Expert Solution
Questions # 68:

A project team member who has the expert knowledge necessary for the project is often absent from meetings. The team member sends a message to the project manager questioning them about the rationale behind some decisions made on the project.

How should the project manager handle the situation?

Options:

A.

Inform the team member that decisions were already made and feedback should have been provided in the past.


B.

Schedule a meeting to review the team member's concerns and revisit the decisions if required.


C.

Explain to the team member that it is mandatory that they increase their participation in project meetings.


D.

Add the team member's concerns to the risk register and discuss them during the next regular meeting.


Expert Solution
Questions # 69:

A project manager is working on an ongoing construction project. The designer notifies the project manager about materials that were not included in the budget due to a technical mistake.

What should the project manager have done to avoid this situation?

Options:

A.

Asked the project sponsor to review the budget


B.

Updated the budget before moving to another stage of the project


C.

Added enough budget to cover all uncertainties


D.

Used past projects as a reference during budget estimations


Expert Solution
Questions # 70:

Project stakeholders are engaged in a discussion on how to achieve the best user experience in the design of a new application. The agile team is divided on the approach. The conflict is more of a collective disagreement than an outright conflict.

What should the project manager do next?

Options:

A.

Apply appropriate conflict resolution techniques to solve the issue.


B.

Call a team meeting to have a formal discussion of the issue.


C.

Allow the team to work through it on their own unless help is needed.


D.

Engage in individual conversation with each team member.


Expert Solution
Questions # 71:

A project manager is managing a project that requires specialized architecture services. This project was identified as a high risk for the

organization. The project manager works with an external architect who is highly specialized. However, the architect will soon resign because they

accepted an offer from another firm.

What should the project manager do next?

Options:

A.

Discuss this with the project team, assess the impact, and decide on the appropriate actions to follow.


B.

Ask the architect for the contact details for their new employer and call their account manager.


C.

Call the account manager and ask them to retain the expert by offering them an incentive.


D.

Escalate the issue to the procurement department and ask them to discuss this with the vendor firm.


Expert Solution
Questions # 72:

The CFO has stated in a conversation with a project team member that they do not believe the project will be a success due to the high cost of implementation.

What should the project manager do?

Options:

A.

Meet with the CFO one-on-one to fully understand their cost concerns.


B.

Ask the project team to look for opportunities to cut project costs.


C.

Carry out a benefit analysis to present at the next project team meeting.


D.

Meet with the CFO and team to remind them of the project's key success measures.


Expert Solution
Questions # 73:

A project manager is managing a project with a cost performance index (CPI) of 1.05 that is trending downward. To maintain on-time completion, the scrum master needs to add 30 additional team members in the next month to enable more sprints. The project manager is concerned because the schedule performance index (SPI) is 1.0.

What is the first step the project manager should take?

Options:

A.

Meet with the project team to forecast the SPI trend to determine if there are funds available to pay the 30 team members.


B.

Quantify the cost for the 30 team members and determine if there is budget available to fund the expanded team.


C.

Inform the project team that since the CPI is trending downward, there are funds available to expand the team.


D.

Engage with the human resources (HR) representative to begin selecting candidates for the 30 open positions.


Expert Solution
Questions # 74:

During the initial stage of a project, the team estimated activities for the next iteration in story points. It was agreed that each story point would be assumed to be equal to one day of effort during project execution. There are some activities estimated as two story points and others estimated as 100 story points.

What should the project manager ask the team to do next?

Options:

A.

Execute the smaller estimated activities.


B.

Resize the story points.


C.

Negotiate the estimation so it gets smaller.


D.

Break down the larger activities into smaller ones.


Expert Solution
Questions # 75:

A project team has finished its first iteration out of six. The iteration's delivery performance (velocity) was 50%.

During the iteration retrospective, the team realizes that the complexity of the work was underestimated.

What should the project manager do?

Options:

A.

Update the issue log and escalate it to the project sponsor.


B.

Meet with the team to review internal actions to resolve the situation.


C.

Ask the technical manager to help the team with the issue.


D.

Ask to replace some team members with more experienced ones.


Expert Solution
Questions # 76:

A software development project completed the initiation phase. The technical design was approved by the project steering committee. Later, it was discovered that the design will impact the company’s production system. A new technical design must be found and this could delay the project by 3 months.

What should the project manager do first?

Options:

A.

Log the technical design delay as a risk in the project risk log.


B.

Set up a steering committee session to review the project delay.


C.

Continue with the approved design so that the project is not delayed.


D.

Ask the steering committee to approve a new technical design.


Expert Solution
Questions # 77:

The team responsible for executing a work package asks the consultant to reconsider the initial project deliverables specified in the contract.

What should the project manager do in this situation?

Options:

A.

Carry out corresponding negotiations in the adjustments of outcomes.


B.

Agree with the consultant to continue without any adjustments.


C.

Pause the project until a satisfactory agreement between both parties is reached.


D.

Explain to the consultant that without adjustments, payment terms will be affected.


Expert Solution
Questions # 78:

After meeting with stakeholders, a project manager working at a computer gaming company is creating a project management plan for the company's newest offering. The project manager learns that the company's main competitor is scheduled to release a similar offering leveraging the newest technology. The project manager fears that the competitor's offering is better in multiple ways compared to the project manager's project.

What should the project manager do?

Options:

A.

Perform a Kano analysis factoring in the competitor's offering and present it to the stakeholders.


B.

Meet with the development team to see what changes will improve the project compared to the competition's deliverable.


C.

Meet with the project team to discuss the concerns and determine how to ensure the project's deliverable can compete with the competitor's.


D.

Note this concern in the risk register and meet with the sales team to identify mitigation options factoring in the competitor's offerings.


Expert Solution
Questions # 79:

A project manager is leading a project that is in the execution phase. Due to a company reorganization, some key project team members are likely to leave the project.

What should the project manager do next?

Options:

A.

Discuss this issue with the affected team members and support them during the transition.


B.

Start looking for replacements as soon as possible to help prevent any schedule slippage.


C.

Engage with the project sponsor to ensure that this change does not affect the project execution.


D.

Determine the impact to the project and implement mitigations per the project management plan.


Expert Solution
Questions # 80:

A project team is working together for the first time. During the first sprint, the project manager was asked to solve a prioritization conflict between the Scrum Master and the Product Owner related to a feature requested by an important customer.

How should the project manager resolve this conflict?

Options:

A.

Refer to the roles and responsibilities for the agile team.


B.

Schedule a meeting with the Scrum Master and Product Owner.


C.

Emphasize that the Scrum Master has the responsibility to conduct the sprint planning.


D.

Contact the customer to understand the request in order to make a decision.


Expert Solution
Questions # 81:

A project manager was recently assigned to a banking IT project. The project team has been developing products using a predictive approach for more than 10 years, but management wants the team to change to an agile approach. The project manager met with the team to introduce the agile approach. Most of the team members complained about changing approaches because the performance of this team has always been above average among the IT teams in the bank.

Which two actions should the project manager take? (Choose two)

Options:

A.

Interview the most resistant team members to persuade them to try to accept an agile approach.


B.

Conduct training sessions with the team so that the team can understand what the agile approach and mindset are.


C.

Ask the team to identify the product backlog and create a kanban board for the team to manage and follow the approach.


D.

Meet with management to explain the team's resistance to the agile approach and request that they formally ask the team to implement agile.


E.

Brainstorm with the team to understand the specifics of the team's project and to identity possible alternative approaches for the team.


Expert Solution
Questions # 82:

A project is on its fifth iteration out of six. One member of the team has left the company unexpectedly.

What should the project manager do next?

Options:

A.

Detail the reason for the project delay in the status report.


B.

Invite the stakeholders to discuss a mitigation plan.


C.

Take on some of the necessary work to minimize the impact.


D.

Register an issue and escalate it to the project sponsor.


Expert Solution
Questions # 83:

A project team wants to change a delivery approach for a project. Team members explain the need for a review of the information-sharing approach to ensure efficient information exchange during the project.

What should the project manager do?

Options:

A.

Ask the project sponsor to decide on the best communication strategy.


B.

Review the stakeholder engagement plan with the project team.


C.

Ask the project sponsor to approve funding for a collaboration tool.


D.

Review the communications management plan with the project team.


Expert Solution
Questions # 84:

A project lead with a strong technical background oversees a project using agile delivery. The product owner asked the project lead to assist with ensuring the benefits of functionality that are built in the sprint are tracked.

What should the project lead advise?

Options:

A.

During the sprint review, ensure that the completed items deliver business benefits.


B.

Present in detail the business benefits delivered in the sprint during the sprint retrospective.


C.

During the daily standup, ensure that each item meets the definition of done (DoD) before accepting it.


D.

Review in detail the criteria for the definition of done (DoD) for each item during the sprint planning.


Expert Solution
Questions # 85:

During the execution of a project, an experienced team member informs the project manager that they cannot take part in all of the scheduled project activities due to a conflicting operational schedule. What should the project manager do?

Options:

A.

Replace the team member with another available resource on the team.


B.

Discuss the situation with the team member's functional manager to see if the schedule can be adjusted.


C.

Check with the project management office (PMO) on the available resources to complete the activities.


D.

Encourage the team member to prioritize scheduled project activities.


Expert Solution
Questions # 86:

A project manager is developing the stakeholder register and is having trouble understanding the motivation of some of the stakeholders. What should the project manager

do to get this information?

Options:

A.

Organize a one-on-one conversation with each stakeholder.


B.

Request stakeholders articulate their motivations at the kick-off meeting.


C.

Email project objectives to all stakeholders and ask for endorsement.


D.

Identify each stakeholder's motivations from the business case.


Expert Solution
Questions # 87:

A project manager is working on a project to develop a new watch at a matrix organization.

Which two key items should the project manager include in their feedback to external stakeholders? (Choose 2)

Options:

A.

Schedule performance index (SPI) for the portfolio


B.

Earned value in terms of resources


C.

Expected return on investment (ROI) for portfolio projects


D.

Earned value in terms of schedule


E.

Earned value in terms of cost


Expert Solution
Questions # 88:

An agile team is developing a new content management system. Some of the team members are struggling to deliver certain features since they have never worked on this type of solution.

What should the project manager do?

Options:

A.

Replace the members with new members who understand the system.


B.

Encourage the team members to make changes directly in the system.


C.

Ask the team to read through all of the available system documents.


D.

Encourage the team to hold a knowledge-sharing session in each iteration.


Expert Solution
Questions # 89:

A project is approaching successful completion, and all stakeholders are really proud of the achieved results. The project management office

(PMO) recommends the project manager to lead the next similar project.

What should the project manager do next?

Options:

A.

Engage key stakeholders to complete and deliver lessons learned.


B.

Select the same stakeholders for the next project to avoid doing knowledge transfer.


C.

Present the project achievements and delegate knowledge transfer to the steering committee.


D.

Request the PMO to manage the lessons learned repository.


Expert Solution
Questions # 90:

A senior project manager is working for a company that is not yet making a profit. However, the company has many innovative projects in development. Most of the project

time lines have slipped, and the staff is overwhelmed .

What should the project manager do to help the company meet their financial objectives?

Options:

A.

Prioritize the projects, giving higher priority to projects that will increase profit.


B.

Make sure the project is fast tracked so that slipped time lines are recovered.


C.

Request that upper management hire additional staff to support the projects.


D.

Ensure that all of the projects are of high quality and are delivered on time.


Expert Solution
Questions # 91:

Before kicking off a high-priority and complex project, what should the project manager do to ensure all project stakeholders are aware of their role scope as it relates to project activities?

Options:

A.

Create a communications management plan.


B.

Create a responsible, accountable, consulted, informed (RACI) chart.


C.

Develop a kanban board.


D.

Send a copy of the project charter to all project stakeholders.


Expert Solution
Questions # 92:

During a design workshop, the engineers ask the project manager about the safety prerequisites for the new product's operating procedures.

What should the project manager do?

Options:

A.

Provide the team with the enterprise environmental factors (EEFs).


B.

Run a benchmark with similar sites to compare compliance constraints.


C.

Look into lessons learned documentation for similar projects.


D.

Hire a specialized engineer to support the design team.


Expert Solution
Questions # 93:

A project manager is leading a hybrid project and is collaborating with the client to develop the project contract.

Some delays have been experienced due to unforeseen technical difficulties and new dependencies. However, the project manager is optimistic about recovering the delays in the upcoming sprints. A key stakeholder asked the project manager if the contract deadlines can be met.

What should the project manager do first?

Options:

A.

Study the contract terms and deadlines to ensure they are not under risk and confirm them with the stakeholder.


B.

Clarify the current work progress, causes for delays, existing risks, and planned corrective actions.


C.

Submit a request for extra time and budget related to the dependencies and technical difficulties.


D.

Ask the stakeholder to remain calm and confirm that they are participating in all team meetings.


Expert Solution
Questions # 94:

A project team needs to create artifacts for an upcoming steering committee.

What should the project manager do first?

Options:

A.

Use templates from an existing project.


B.

Ask the project management office (PMO) for guidance.


C.

Surveying peers to understand what templates they have used.


D.

Lead the project team in finding the best templates.


Expert Solution
Questions # 95:

A team is holding the first demonstration of the software built to date on a medium-sized project The product owner has uncovered a number of issues they would like to be addressed before providing approval

How should the project manager approach this problem?

Options:

A.

Plan to address the issues through backlog grooming and incorporate them into the next sprint


B.

Refer the product owner to the change management plan, then escalate to the steering committee


C.

Refer the product owner to the signed business requirement document and explain that the current plan cannot facilitate these changes


D.

Tell the product owner the issues will be addressed in the second version of the software


Expert Solution
Questions # 96:

A project manager invites the company CEO, sponsor, team members, and an external client representative to a meeting to review the project management plan. The project manager starts to present the budget but the CEO suddenly asks to end the meeting

What should the project manager have done to avoid this situation?

Options:

A.

Reviewed the communications management plan before inviting an external client representative to the meeting


B.

Reviewed the cost management plan with internal participants and CEO prior to inviting an external client representative to the meeting


C.

Performed a root cause analysis with the external client representative and documented the findings in the lessons learned register


D.

Sent the presentation slides to internal participants first and then to the external client representative prior to the meeting


Expert Solution
Questions # 97:

An agile team member received certification on a new tool: however, this learn member is complaining that the rest of the team is not using the tool due to lack of knowledge How should the servant leader apply emotional intelligence to leverage this situation to benefit the project?

Options:

A.

Request budget to reward the team member so others will be motivated to obtain the same certification


B.

Promote the team member to product owner to leverage the new knowledge with the clients


C.

Provide an incentive to team members who begin using the new tool on this project.


D.

Ask the team member to use their recently acquired knowledge to develop and provide training to the team


Expert Solution
Questions # 98:

During the execution of a project the project manager notices that only one team member has one of the technical skills needed to build the product The project manager is afraid this might have a future impact on the quality and schedule because most of the upcoming activities will require at least three people with this specific skill.

What two actions should the project manager take to prevent the team from being unqualified? (Choose two)

Options:

A.

Exclude the activities from the roadmap


B.

Encourage working in pairs and knowledge sharing


C.

Teach the entire team the new skill.


D.

Facilitate a training event with an external trainer


E.

Increase the time estimates on the activities that require such abilities


Expert Solution
Questions # 99:

The project sponsor of a major initiative is consistently changing the prioritization of modular work packages The team is used to three week sprints and is becoming increasingly frustrated with the daily changes in scope>

What should the project manager do?

Options:

A.

Move to a Kanban strategy so that work can be reallocated more easily


B.

Decrease the sprint cycle to the average repriontization request by calculating it in days


C.

Set up a meeting with the project team and ask for their opinion on what to do


D.

Set up a meeting with the sponsor to explain the importance of keeping a strict sprint cycle


Expert Solution
Questions # 100:

A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two)

Options:

A.

Risk steering committee


B.

Functional managers


C.

Board of directors


D.

Advisory team panel


E.

Chief executive officer


Expert Solution
Viewing page 2 out of 12 pages
Viewing questions 51-100 out of questions