Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 2 out of 13 pages
Viewing questions 51-100 out of questions
Questions # 51:

A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.

What should the project manager do to address the concem9

Options:

A.

Provide team-building activities so that the team can learn how to overcome disruptive behavior


B.

Inform the disruptive team member's functional manager that the disruptive behavior should be stopped immediately


C.

Request a meeting with the disruptive team member and help to resolve the issue


D.

Encourage self-governance and ask the concerned team member to speak to the disruptive team member directly


Expert Solution
Questions # 52:

During a project gate review meeting, it is identified that one of the project

deliverables will require corrective actions to meet the project quality requirements. What

should the project manager do first?

Options:

A.

Update the risk register and implement the approved risk response plan for qualitydeviations.


B.

Identify the resources that were responsible for the deliverable and request a teamdevelopment plan.


C.

Update the issue log, identify the involved stakeholders, and assign resources to thecorrective actions.


D.

Submit a change request to update the project quality requirements for the involvedproject deliverable.


Expert Solution
Questions # 53:

A project manager was replaced in the early phases of a new project. The new project manager discovers that the business team is not supporting the project. After

discussing these concerns with the team, it is determined that the project does not have the full support of senior management.

What should the new project manager do next?

Options:

A.

Send out a status report describing the situation to the stakeholders and request general assistance.


B.

Request the business team to clearly define their issues with the project work completed to date.


C.

Study the stakeholder analysis to understand which stakeholder holds the most influence and seek their assistance.


D.

Ask senior management to be more involved with the project and to provide their full support.


Expert Solution
Questions # 54:

A project manager for an iterative project received feedback from an on-site team member that the virtual team was not meeting the deliverables on time. The project manager gathered details on what the status report should contain m order to track deliverables

What is the remedial action the project manager should take?

Options:

A.

Perform stakeholder engagement with the virtual team


B.

Add status reports to the communications management plan


C.

Convene an on-site meeting for both of the teams


D.

Add status report creation as a product backlog item


Expert Solution
Questions # 55:

An organization is producing a product using a hybrid approach with several phases. Some of the phases are planned to be executed in predictive and some in agile. During the agile phase, the project manager notices that the team members sometimes unknowingly work on the same task.

What should the project manager do?

Options:

A.

Communicate the task assignments to the team members in a clear manner.


B.

Verify that the product owner has made the task assignments clear.


C.

Confirm that the agile coach has made the task assignments clear.


D.

Verify that the team members have made the task assignments clear.


Expert Solution
Questions # 56:

While monitoring a project at a work site, the project manager notices that the site team’s work breaks have increased by a few minutes every week. How should the project

manager approach this?

Options:

A.

Reduce payment to the workers due to their extended breaks.


B.

Issue a formal written warning to all hourly workers for their break tardiness.


C.

Have a meeting with the team to discuss the issue and propose solutions.


D.

Dismiss some of the workers for failing to adhere to the break policy.


Expert Solution
Questions # 57:

A project manager has just been appointed to a project that has two major deliverables. Both deliverables have the same level of priority and are to be delivered at the same time. The members of the team are complaining about the lack of information regarding which deliverable needs to be finished first.

What should the project manager do?

Options:

A.

Ask key stakeholders to cancel the project due to the difficulty of executing both deliverables at the same time.


B.

Ask the team to start working on the easiest deliverable first so they gain experience to execute the second deliverable.


C.

Meet with the project sponsor and key stakeholders to assess each deliverable's value to the organization and set execution priorities.


D.

Require that the project team execute both deliverables at the same time, since this was requested and approved in the project charter.


Expert Solution
Questions # 58:

A project schedule risk has turned into an issue. The project manager foresees delays in project execution.

What should the project manager do to resolve the issue?

Options:

A.

Update the risk management plan and send it to the project team.


B.

Update the schedule baseline to the new project time line.


C.

Escalate the issue to senior leadership for resolution.


D.

Work with relevant stakeholders to determine possible solutions.


Expert Solution
Questions # 59:

Due to a tight schedule, a project team member suggests skipping the quality check of a minor deliverable. What should the project manager do?

Options:

A.

Evaluate the impact of skipping the quality check for the deliverable.


B.

Seek approval from the sponsor on an extension of the project schedule,


C.

Seek approval from the quality board to skip the quality check.


D.

Ask the team member to work overtime to complete the quality check.


Expert Solution
Questions # 60:

A project manager finds an unexpected issue halfway through a customer's protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.

What should the project manager do?

Options:

A.

Meet with the project team to discuss internally whether they think cost is more important to the customer than the timeline


B.

Adjust the timeline since in the past the customer would not pay any additional costs then inform the customer of the change


C.

Inform the customer of the issue and discuss the options so that they are able to make a decision on cost versus timeline


D.

Absorb the additional cost for the additional resources internally so that the project completes within the timeline


Expert Solution
Questions # 61:

An agile team is conducting a sprint retrospective and wants to focus on the practices that allowed them to recover after a bad start Please click on the area of the burndown chart that the team should focus on.

Question # 61


Expert Solution
Questions # 62:

A project manager assigned to an engineering construction project is receiving questions from the site engineers. Several questions are related to carrying out activities to meet timelines that compromise the work crew's safety. When reviewing these questions, the project manager realizes that the engineers do not (eel empowered to make decisions.

How should the project manager address this?

Options:

A.

Consult the previous project manager to discuss how they managed these questions.


B.

Ensure all engineers are aware that questions should only be submitted in their weekly reports.


C.

Email the company vision to the engineers and tell them they need to meet deadlines


D.

Reinforce to all engineers the company vision of a safety-first approach to project activities.


Expert Solution
Questions # 63:

A project team is reviewing solved project issues from the last phase of a project. The lead risk analyst points out that the next phase of the project includes a critical element with some

reserves needed

What should the project manager do to successfully complete the next phase?

Options:

A.

Request a reserve analysis and update the risk management plan


B.

Update the risk response plan to include the needed reserve


C.

Perform a schedule network analysis to avoid any critical path delays


D.

Review the risk response plan to verify inclusion of the needed reserve


Expert Solution
Questions # 64:

A project manager has been assigned to lead an IT project to store information on sold lottery tickets. During the project execution, a failure in the

system caused 10 numbers to be sold two times. This happened during the month of greatest demand because the prize was the highest of the

year. The project team is concerned that one of those tickets could be the winner.

What should the project manager do first?

Options:

A.

Reassure the sponsor by explaining the probability of this risk materializing is extremely low.


B.

Carry out tests to verify that the system does not fail again due to the high occurrence of events.


C.

Review the list of risks to verify that this issue was considered and execute the detailed action plan.


D.

Inform the sponsor about the issue and make a request for sufficient funds to be made available.


Expert Solution
Questions # 65:

After 1 year Into the life cycle of an ongoing residential project, an announcement was received from the municipality regarding a new regulation that will greatly impact the project's schedule and budget. What should the project manager do next?

Options:

A.

Perform a qualitative risk analysis and update the risk register.


B.

Submit a change request through the Integrated change control process.


C.

Update the issue log and discuss It in the next steering committee meeting.


D.

Estimate the associated costs and increase the project budget accordingly.


Expert Solution
Questions # 66:

A protect team is working remotely on a solution The client wants the solution as soon as possible and is uncomfortable because the team members are not colocated In addition the client expressed concerns about the understanding of the project context and the team's decision-making process

What should the project manager do?

Options:

A.

Update the communications management plan to satisfy the client's request


B.

Request the client to attend the daily meetings with the project team


C.

Encourage the client to interact with the protect collaboration platform


D.

Ask the product owner to frequently communicate with the stakeholders


Expert Solution
Questions # 67:

A company strictly uses an agile approach, and the backlogs are continuously updated. A new project lead is hired and feels uncomfortable sharing some of the product's vital information with the team and the product owner.

What does the project lead need to do to prevent a risky situation in the next iterations?

Options:

A.

Keep the project focused and executed in silos for better outcomes.


B.

Report the concern to the agile project management office (PMO),


C.

Inform the product owner of the concern so that i can be addressed.


D.

Open up to the team to work collaboratively to achieve the outcomes.


Expert Solution
Questions # 68:

project manager for a defense software application has a culturally and gender-diverse team with a short project time line Considering the project will be stressful what skill should the project manager use to monitor the team's performance?

Options:

A.

Coercion


B.

Conflict resolution


C.

Emotional intelligence


D.

Negotiating


Expert Solution
Questions # 69:

A company has rolled out the latest retail management system, and the project has been handed over to operations. The operations team finds that many of the day-to-day requirements are not covered in the system, and support for the project has limited hours, The project team has dissolved and the contract resources are no longer working on the project. As a result, the operations team has been facing numerous customer issues.

What should the project lead have done initially to avoid this situation?

Options:

A.

Reviewed the project management plan


B.

Created a detailed operations manual


C.

Increased support hours for the hours of operation


D.

Involved operations stakeholders during planning


Expert Solution
Questions # 70:

A new project needs to be submitted for urgent funding approval. The project, which will use a new technology, is vital to the organization. The entire Scrum team has worked together for over 3 years on multiple projects and delivered the previous project under the approved budget.

Which estimation technique should the project manager implement in this context?

Options:

A.

Budget estimate


B.

Definitive estimate


C.

Story points


D.

Order of magnitude


Expert Solution
Questions # 71:

A customer calls the project manager to express concern about a project team

member who has been making changes within the live environment without approval. The

team member mentioned that the customer called and asked them to make the changes.

What should the project manager do next?

Options:

A.

Reinforce the value of documenting and approving all change requests and ask thecustomer to issue these through the agreed channels.


B.

Organize a meeting to mediate the relationship between the customer and the teammember to ensure no feelings are hurt.


C.

Ask the customer to email all requests directly to you and you will ensure they areactioned by the correct team member.


D.

Explain to the customer that the team member was just trying to help and the changescan be reverted if necessary.


Expert Solution
Questions # 72:

A team lead has been highly engaged and involved in a project and is operating without a chain of command or authority levels What is the team lead dang1?

Options:

A.

Modeling directive leadership


B.

Modeling commanding leadership


C.

Modeling adaptive leadership


D.

Modeling servant leadership


Expert Solution
Questions # 73:

A project manager is managing two integrated projects in a program A key integration point is misaligned, which has resulted in delays. One of the team's integration leads is a subject matter expert (SME) m this integration area. The other team's integration lead is not a SME but is more senior and has worked on the project longer Both team leads are blaming each other

What should the project manager do first to resolve this situation?

Options:

A.

Assign the resolution of the issue to the senior integration lead who has worked on the project longer


B.

Meet with both integration leads to understand the root cause and determine a resolution


C.

Escalate the issue to the program architect who developed the integration plan


D.

Assign the resolution of this issue to the integration lead who is a SME


Expert Solution
Questions # 74:

During a scope validation exercise toward the end of a project, a project manager realizes that some operational project requirements were not captured in the project scope of work. Although completing these Items will have an Impact on the project's completion date. It will Increase the likelihood of customer acceptance.

What should the project manager do to address the issue?

Options:

A.

Issue a change request to remove items from the scope of work and keep the project on schedule.


B.

Issue a change request to include the additional scope, and track the completion of the work items.


C.

Document the issue in the lessons learned document, and discuss this with the project sponsor.


D.

Arrange to pass the cost to the operational area since the customer will benefit.


Expert Solution
Questions # 75:

A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project.

What should the project manager do to address this issue?

Options:

A.

Negotiate the payments with the supplier and remind them of their long-term association


B.

Penalize the supplier according to the contract's service level agreement (SLA)


C.

Hire another information security supplier and incentivize them for speedy delivery


D.

inform the relevant stakeholders of this challenge and seek their support


Expert Solution
Questions # 76:

A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?

Options:

A.

Stakeholder analysis


B.

Resource needs analysis


C.

Accommodations assessment


D.

Team member assessment


Expert Solution
Questions # 77:

A team realizes that there is no access to data that the project depends on to complete the current iteration. This dependency was known; however, the team is unsure of the available options to remove this obstacle.

What should the project manager do next?

Options:

A.

Guide the team to determine alternatives.


B.

Move the dependent task to the next iteration.


C.

Escalate the issue to the company's IT manager.


D.

Escalate the issue to the project sponsor.


Expert Solution
Questions # 78:

A project team is working on an agile software development project. The project manager is concerned that the virtual team may not be as effective as a colocated team at headquarters.

Which two actions should the project manager leverage to ensure the team is meeting performance expectations?

(Choose two)

Options:

A.

Hold daily virtual meetings to review progress.


B.

Implement time-keeping software for team members.


C.

Task functional managers to drive accountability.


D.

Utilize a web-based kanban board.


E.

Require a monthly individual status report.


Expert Solution
Questions # 79:

An engineer working on a project team has tasks that require an additional skill that the engineer does not have a designer on the team is experienced with this skill from previous jobs and is willing to teach this skill even though it is not part of the current work

What should the project manager do?

Options:

A.

Escalate the situation to the engineer's manager


B.

Request external training for the engineer


C.

Request external training for the engineer and designer


D.

Allow the engineer and designer to cross-train with each other


Expert Solution
Questions # 80:

A project manager is tasked with large deliverables that require work by several top developers over the next few weeks Because of the size and complexity of the deliverables the work cannot be assigned to a single person

What should the project manager do first?

Options:

A.

Request additional developers to join the project team through the change cannot process


B.

Break down the deliverable by using the work breakdown structure (WBS) process to make it more manageable for task assignment


C.

Assign the entire deliverable to the first available developer to lead and have them assign the work to the remaining developers


D.

Include the situation as a risk in the risk register identify risk impacts and possible mitigations, and monitor closely


Expert Solution
Questions # 81:

A project manager has noticed that a critical team member is consistently arguing

with a client. This has started to have a negative effect on the meetings.

How should the project manager address this?

Options:

A.

Explain the impact of the scenario to the project team member.


B.

Remove the project team member from all future meetings.


C.

Talk to the client privately to highlight the situation.


D.

Recommend a performance improvement plan to the project team member.


Expert Solution
Questions # 82:

A project is about to close and the project manager is p Set up a meeting to perform a root cause analy reparing a draft of the project closure report. The project sponsor has approached the project manager to stay on longer to ensure the benefits in the charter are tracked as completed However, some of the benefits will not be realized until 1year after project implementation.

What should the project manager do?

Options:

A.

Explain to the project sponsor that the project manager is only accountable for managing the project scope budget quality and schedule


B.

Document who will be tracking benefits realization what will be tracked and when it will be tracked in the project closure report


C.

Explain to the project sponsor that they are accountable for tracking benefits realization after project completion


D.

Discuss extending the project manager's allocation to the project until all benefits are realized with the project management office (PMO)


Expert Solution
Questions # 83:

A project has recently Kicked off. The project manager observes that thete are different expectations among the project team members. These growing misunderstandings are affecting team productivity.

Which document should the project managefve?

Options:

A.

Project charter


B.

Stakeholder register


C.

Team charter


D.

Project organization charts


Expert Solution
Questions # 84:

Eight highly qualified experts have been assembled to work for a 6-month period on an a specific aspect of an organization's product development process. How should the

project manager support this team to succeed?

Options:

A.

Hand over control of specific aspects of their roles as experts and let them agree on their own timelines and targets.


B.

Bring in a senior colleague who is also an expert to ensure the team is on track to achieve the goals and objectives.


C.

Define roles and targets for all team members and regularly follow up with one-to-one meetings to review progress.


D.

Work with the team members to define the overall objective and support them to engage around the goal.


Expert Solution
Questions # 85:

A project manager is working on a complex project and is unsure about planning, executing, monitoring and controlling the project. Match the phrase on the left with the correct statement on the right.

Question # 85


Expert Solution
Questions # 86:

A project team has been formed and the tasks have been assigned to each team member All team members have agreed to follow a hybrid protect approach. What should the project manager do to ensure the team performs as an organized unit?

Options:

A.

Advise the team to adjust their work habits and behaviors to allow for better conflict resolution


B.

Call a team meeting to discuss team members' strengths and weaknesses


C.

Establish rules and regulations for team members with consequences if the goals are not reached


D.

Establish team behavior and develop an understating of how to work together


Expert Solution
Questions # 87:

Organizational downsizing has resulted in the key subject matter expert (SME) resource leaving a multiyear project. What should the project manager do?

Options:

A.

Update the stakeholder register.


B.

Refer to the resource management plan.


C.

Consult the project sponsor.


D.

Modify the statement of work (SOV).


Expert Solution
Questions # 88:

An organization is transitioning to an agile delivery approach. There is only one project that is being used as a pilot for the new approach. The project management office (PMO) manager has asked the project lead how communications with the project team and the stakeholders will be managed.

What should the project lead recommend?

Options:

A.

Send the weekly report to the PMO and the product owner, and use a kanban board for the project team.


B.

Send weekly reports to the PMO, and use a kanban board for the product owner and the project team.


C.

Invite the PMO manager to the daily standup with the project team and product owner.


D.

Send weekly reports to all stakeholders, including the project team and the product owner.


Expert Solution
Questions # 89:

A project team member reads in a financial newspaper that the main project supplier is facing some financial difficulties and communicates this to the project manager. What should the project manager do?

Options:

A.

Add the situation to the project risk register to be managed


B.

Identify competitors that are qualified to replace the current supplier


C.

Inform the purchasing department that manages the supplier relationship


D.

Use the issue log to record the situation immediately


Expert Solution
Questions # 90:

A hybrid project is experiencing several issues with both the agile delivery of the

product as well as the predictive development of a marketing strategy. What should the project manager do to receive feedback from stakeholders located in different time zones?

Options:

A.

Refer to the stakeholder engagement plan.


B.

Set up a conference call for all stakeholders.


C.

Refer to the communications management plan.


D.

Send an email to all stakeholders.


Expert Solution
Questions # 91:

A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.

What should the project manager do next?

Options:

A.

Request the project sponsor to fund this change as it is a new regulation, then order the materials in order to start working.


B.

Assess the impact of the required change and consult with the executive sponsors to determine the best course of action.


C.

Ask the designers to start designing a solution for this new requirement while the project is running and determine the funding for this change.


D.

Have the company's lawyers write to the municipality and reject the change as it was not part of the scope approved by the municipality.


Expert Solution
Questions # 92:

A key project team member has exhibited high interest in a project. The input from

this person has been very useful, and the project is steadily progressing. Suddenly, this individual's participation decreases, and activities that they were responsible for are not being completed within the planned period.

What should the project manager do?

Options:

A.

Reallocate tasks for the team member of concern so that work is handled by another team member.


B.

Schedule a meeting to discuss recent observations with the team member.


C.

Organize a team-building session with all of the team members.


D.

Consult the resource allocation matrix to see if the team member is still required for theproject.


Expert Solution
Questions # 93:

A project manager is asked to develop maintenance planning software for a power plant. A similar project was executed by another department in the organization that was later closed due to low performance. The project manager is concerned about the project's performance and wants to

take action in advance to ensure the project succeeds.

What should the project manager do?

Options:

A.

Evaluate the project risk and add external experts to address the potential risks.


B.

Inform the project sponsor about the risk and try to convince them to withdraw from the project.


C.

Continue executing the project as planned and add more resources if they are required.


D.

Review the lessons learned on similar projects so that they do not fall back into the same pattern.


Expert Solution
Questions # 94:

The Scrum team working with the quality department has been shifting away from the Business unit due to unclear product requirements. It is now the third sprint and both teams have been at a standstill for a few days.

What should the project leader do to solve this situation?

Options:

A.

Analyze the problem with both teams to figure out If pan of the work must be redone.


B.

Select new team members in an effort to obtain fresh ideas to solve the impasse.


C.

Demand that the business team stop wasting time and define final requirements for the product.


D.

Tell the business team and Scrum team to continue following the initial plan.


Expert Solution
Questions # 95:

A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.

What should the project manager do?

Options:

A.

Use the agile approach in the new project and schedule agile training for those stakeholders who are new to this approach


B.

Continue to use the predictive approach m the new project since it is the approach the stakeholders are familiar with using


C.

Share the pros and cons of adopting an agile approach for the new project only with the team and ask them to decide which approach to use


D.

Share and discuss the pros and cons of adopting agile with the stakeholders and choose the approach they prefer for the new project


Expert Solution
Questions # 96:

A project manager learns from a marketing analyst that a competitor just published a press release announcing a product launch using a specific innovation The project manager is concerned because the company is initiating a project involving the same innovation A key goal of the new project is that the product will be the first to market won the innovation

What should the project manager do next?

Options:

A.

Document the issue in the issue log and escalate to the project sponsor


B.

Inform the project sponsor and suggest canceling the project


C.

Review the project goals and eat criteria m the project charter


D.

Ask the leader of research and development to decide on next steps


Expert Solution
Questions # 97:

A project manager is building a team to work on a service integration project that will transition technology management services from company A to company B. The project team will consist of members from both companies. Prospective team members for the project are located all over the world, have different types of technology backgrounds, and use different approaches for work.

How should the project manager build a cohesive, high-performing team?

Options:

A.

Organize the team members into several kick-off sessions based on technology type.


B.

Review the list of team members’ skills and understand how they will work together to deliver the project outcomes.


C.

Ask the human resources (HR) department to arrange interview meetings to select the team.


D.

Ask prospective team members to write a short biography explaining how they can contribute to the team's success.


Expert Solution
Questions # 98:

A few key stakeholders are concerned about how the prefect team is planning to develop some features tor a new product. They know that the requirements associated with these features are unstable but are also highly strategic for adding value to the product and the customer.

What should the project manager do?

Options:

A.

Suggest an agile approach to refine these requirements and prioritize them according to the project objectives


B.

Validate the prioritization of all requirements with the sponsor and share the results with the stakeholders


C.

Review the project governance to validate the policies procedures and guidelines used to prioritize the project


D.

Ask the stakeholders to refine these requirements at a level of detail that becomes more stable and measurable


Expert Solution
Questions # 99:

A project manager has decided to stop activities that do not add value to a project that has a risk of running over budget. A functional manager disagrees with this decision, especially when the team is performing product testing for highly sensitive end users. The functional manager escalated the issue to the project sponsor so that the team can resume activities.

How should the project manager have handled the situation?

Options:

A.

Collaborated with the functional manager to determine which critical activities could be accommodated by the budget


B.

Engaged with the project sponsor to ensure support for the project manager's decision


C.

Conducted a meeting with the functional manager to explain why the activities needed to be stopped


D.

Convinced the functional manager to stop the activities that will run beyond the budget


Expert Solution
Questions # 100:

A project manager is leading a project to modemize the information technology of a bank. The project manager needs to determine how the project stakeholders should communicate, and has discussed the various options with the project team.

What should the project manager do to communicate with the stakeholders?

Options:

A.

Provide updates to the project sponsor to review and distribute to each stakeholder.


B.

Use a single communication medium such as video teleconferencing to limit confusion.


C.

Use a variety of communication methods that respect cultural, practical, and personal preferences.


D.

Send frequent updates via email to each stakeholder because this is an information technology project.


Expert Solution
Viewing page 2 out of 13 pages
Viewing questions 51-100 out of questions