New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 79 Topic 8 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 79 Topic 8 Discussion

PMP Exam Topic 8 Question 79 Discussion:
Question #: 79
Topic #: 8

A project manager for an agile project is concerned that the team has been losing momentum over the last iterations. Which two tools should the project manager use to

analyze team performance? (Choose two)


A.

0Project schedule


B.

Product backlog bumup chart


C.

Work breakdown structure (WBS)


D.

Cumulative flow diagram of completed features


E.

Burndown chart


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.