A project manager for an agile project is concerned that the team has been losing momentum over the last iterations. Which two tools should the project manager use to
In agile project management, the cumulative flow diagram and the burndown chart are essential tools for analyzing team performance. The cumulative flow diagram provides a visual representation of work items in various stages of a process, allowing the project manager to identify bottlenecks or work in progress limits. The burndown chart, on the other hand, shows the amount of work that has been completed and the work remaining over time, offering insights into whether the team is on track to complete the project in the desired timeframe.
= Agile Practice Guide1, Metrics for Agile Projects: Finding the Right Tools for the Job2, Team Performance Domain - PMBOK 7 Study3.