PMI Project Management Professional (2025 Version) PMP Question # 79 Topic 8 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 79 Topic 8 Discussion

PMP Exam Topic 8 Question 79 Discussion:
Question #: 79
Topic #: 8

A customer complains that a software update project is failing to deliver value according to the original scope. What should the project manager do to resolve the problem?


A.

Ensure that the project issue log is up-to-date with the customer's issues related to the missed stories.


B.

Ensure that the project change log is up-to-date with the stories based on the missed requirements.


C.

Ensure that the project backlog has the features and stories prioritized correctly.


D.

Ensure that the project risk register is current and reflects the impacts posed by stories not delivered.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.