PMI Project Management Professional (2025 Version) PMP Question # 81 Topic 9 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 81 Topic 9 Discussion

PMP Exam Topic 9 Question 81 Discussion:
Question #: 81
Topic #: 9

During the service procurement process for a strategic project, only one bidder submitted a bid. The price of the offer is significantly large and the project sponsor is not convinced that the return on investment (ROI) can be achieved.

How should the project manager address this issue?


A.

Re-visit the project charter and seek other alternatives.


B.

Proceed and issue the purchase order as this project is important.


C.

Speak with the CEO and ask for their support to approve the offer.


D.

Analyze the bounds of negotiations for project agreements.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.