PMI Project Management Professional (2025 Version) PMP Question # 82 Topic 9 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 82 Topic 9 Discussion

PMP Exam Topic 9 Question 82 Discussion:
Question #: 82
Topic #: 9

A virtual project team is working on a multinational project with a risk management strategy. An unexpected situation occurs in one of the project countries, creating the possibility that project operations will shut down for at least two months.

What should the project manager do to address this risk?


A.

Relocate the project to another country that is not shutting down.


B.

Evaluate the possibility of having another country complete the task.


C.

Identify additional team members who are able to complete the task.


D.

Determine if the project has built-in slack to remain on schedule.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.