Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 82 Topic 9 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 82 Topic 9 Discussion

PMP Exam Topic 9 Question 82 Discussion:
Question #: 82
Topic #: 9

A project is about to close and the project manager is p Set up a meeting to perform a root cause analy reparing a draft of the project closure report. The project sponsor has approached the project manager to stay on longer to ensure the benefits in the charter are tracked as completed However, some of the benefits will not be realized until 1year after project implementation.

What should the project manager do?


A.

Explain to the project sponsor that the project manager is only accountable for managing the project scope budget quality and schedule


B.

Document who will be tracking benefits realization what will be tracked and when it will be tracked in the project closure report


C.

Explain to the project sponsor that they are accountable for tracking benefits realization after project completion


D.

Discuss extending the project manager's allocation to the project until all benefits are realized with the project management office (PMO)


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.