PMI Project Management Professional (2025 Version) PMP Question # 84 Topic 9 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 84 Topic 9 Discussion

PMP Exam Topic 9 Question 84 Discussion:
Question #: 84
Topic #: 9

A project manager is leading a highly visible project with a critical time constraint. Frequent scope changes have been well-managed with change control, but there have been misunderstandings among project team members.

What should the project manager do?


A.

Communicate to the team the need to organize common ground rules.


B.

Organize training sessions and bonding activities for all team members.


C.

Communicate changes regularly to ensure all team members are aligned.


D.

Introduce new products and team support tools during project preparation.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.