PMI Project Management Professional (2025 Version) PMP Question # 84 Topic 9 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 84 Topic 9 Discussion

PMP Exam Topic 9 Question 84 Discussion:
Question #: 84
Topic #: 9

An agile project is in its sixth iteration out of 10 After the iteration review, the team receives feedback from the stakeholders that could result in a change in the product What two actions should the project manager take? (Choose two)


A.

Ask the stakeholders about the priority of this change


B.

Ask the product owner to review the product backlog


C.

Ask the team members to analyze the impact of this change


D.

Ask the sponsor to approve the change request


E.

Ask the team members to include the change in the next iteration


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.