Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 226 Topic 23 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 226 Topic 23 Discussion

PMP Exam Topic 23 Question 226 Discussion:
Question #: 226
Topic #: 23

A project is nearing completion when a critical resource can no longer work on the project. A temporary replacement is brought in from an external company to take over the role; however, complaints are soon received from other team members about this person's unprofessional conduct and behavior.

What should the project manager do first?


A.

Discuss the team charter with the new team member to align them with the agreed-upon conduct within the team.


B.

Report the new team member to human resources (HR) for disciplinary actions.


C.

Hold one-on-one meetings with the new team member and the rest of the team members to align the team charter.


D.

Ask the contracting agency to replace the temporary team member.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.