Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 226 Topic 23 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 226 Topic 23 Discussion

PMP Exam Topic 23 Question 226 Discussion:
Question #: 226
Topic #: 23

A project manager is assigned midway through a project. The team members are in

different locations across the country and they are unable to meet in-person often. During a status review meeting, one of the stakeholders highlighted that they were unaware of the status for the project deliverables.

What should the project manager do first?


A.

Request the project team include the stakeholder's details and make sure the projectstatus reports are shared with the stakeholder.


B.

Schedule a meeting with the stakeholder and include the stakeholder's needs in the project management plan.


C.

Review the stakeholder management plan and update the stakeholder register forincorporation in the project management plan.


D.

Review the communications management plan and verify whether the stakeholder's needs are captured in the project management plan.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.