PMI Project Management Professional (PMBOK 7th Version) PMP Question # 616 Topic 62 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 616 Topic 62 Discussion

PMP Exam Topic 62 Question 616 Discussion:
Question #: 616
Topic #: 62

A project manager works at an organization that is transitioning to agile The development team has recommended using a burndown chart to provide visibility on project progress to all stakeholders.

What should the project manager do to ensure effective communication throughout the project?


A.

Advise the project management office (PMO) to use the burndown chart as the single communication channel.


B.

Develop a communications management plan for each category in the stakeholder register.


C.

Include the burndown chart in a monthly report that is distributed to all stakeholders.


D.

Postpone the recommendation since the organization does not currently have a defined agile methodology.