PMI Project Management Professional (2025 Version) PMP Question # 76 Topic 8 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 76 Topic 8 Discussion

PMP Exam Topic 8 Question 76 Discussion:
Question #: 76
Topic #: 8

Two project team members are updating the schedule but cannot reach an agreement on when two milestones are due. Each team member believes they are correct based on the documents they have available.

What should the project manager do first to finalize the schedule?


A.

Engage the two team members to investigate the reasons each believes that their documents are correct.


B.

Update the schedule so it is available for team members to continue the work and figure out the discrepancy later.


C.

Ask the two team members to meet to work the discrepancy out and let the project manager know the outcome.


D.

Ask the team members to send the documents and apply expert judgment to update the schedule.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.