Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 76 Topic 8 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 76 Topic 8 Discussion

PMP Exam Topic 8 Question 76 Discussion:
Question #: 76
Topic #: 8

A project manager notices that a project participant seems frustrated and expresses themselves loudly at status meetings and later discovers that the participant is hearing impaired. Which process should the project manager have used at the start of the protect that would have identified this situation?


A.

Stakeholder analysis


B.

Resource needs analysis


C.

Accommodations assessment


D.

Team member assessment


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.