New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 76 Topic 8 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 76 Topic 8 Discussion

PMP Exam Topic 8 Question 76 Discussion:
Question #: 76
Topic #: 8

A project lead has asked a project team to update a 200-page project report and send it to the project sponsor. The team mentioned that nobody reads the report and it takes time away from higher priority work. The project lead responded that they have to show all the work that they performed in every iteration.

What should the project lead do first?


A.

Summarize the project report so it can be more efficient to read and send it to the project sponsor.


B.

Ensure the communications methods, channels, frequency, and level of detail for the stakeholders are what is needed.


C.

Reinforce the need to document and provide updated information to make the process transparent.


D.

Include a task in every iteration to allocate time for the project team to complete the documentation updates.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.