PMI Project Management Professional (2025 Version) PMP Question # 76 Topic 8 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 76 Topic 8 Discussion

PMP Exam Topic 8 Question 76 Discussion:
Question #: 76
Topic #: 8

In a standup meeting a team member has been providing the same update for five consecutive days. The task which is on the critical path is now at risk tor delaying the schedule. What should the project manager do?


A.

Reassign the task to another member of the team


B.

Support the team member by providing one more resource to complete the task immediately


C.

Ask the team member if there is an impediment and help to remove the blockers


D.

Keep the project sponsor informed about the delay


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.