New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 75 Topic 8 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 75 Topic 8 Discussion

PMP Exam Topic 8 Question 75 Discussion:
Question #: 75
Topic #: 8

A newly hired project team lead was assigned a project using a hybrid delivery approach. As the project onboards a lot of new team members, the lead feels overwhelmed with the effort of explaining the project delivery process to each new team member.

What should the project lead do?


A.

Use Pareto techniques to identify the knowledge required by the majority of the team.


B.

Recommend putting the project temporarily on hold and focus on onboarding and training.


C.

Develop a training curriculum and schedule training delivery throughout the project.


D.

Document the processes and organize a week-long, off-site meeting with the project team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.