PMI Project Management Professional (2025 Version) PMP Question # 75 Topic 8 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 75 Topic 8 Discussion

PMP Exam Topic 8 Question 75 Discussion:
Question #: 75
Topic #: 8

A project manager is reviewing several potential changes to the contract with third-party vendors.

Which two changes could trigger a modification to the vendor contractual obligations? (Choose 2)


A.

Adding new resources to the change control team


B.

Adding vendors to increase flexibility and availability of work crews


C.

Introducing additional requirements based on new regulations


D.

Modifying a supplier's name due to a vendor acquisition


E.

Replacing a material type based on product availability


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.