Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 75 Topic 8 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 75 Topic 8 Discussion

PMP Exam Topic 8 Question 75 Discussion:
Question #: 75
Topic #: 8

A supplier is hired to provide information security services for a project. The supplier has decided not to provide this service any longer since they have not been paid on time. Their services are critical and this decision will affect the outcome of the project.

What should the project manager do to address this issue?


A.

Negotiate the payments with the supplier and remind them of their long-term association


B.

Penalize the supplier according to the contract's service level agreement (SLA)


C.

Hire another information security supplier and incentivize them for speedy delivery


D.

inform the relevant stakeholders of this challenge and seek their support


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.