PMI Project Management Professional (2025 Version) PMP Question # 75 Topic 8 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 75 Topic 8 Discussion

PMP Exam Topic 8 Question 75 Discussion:
Question #: 75
Topic #: 8

A project manager is working on a software product that will be installed across all levels of the client's organization. The client's executive sponsor insists that only stakeholders at the highest level of the company will be involved in the planning phase.

What should the project manager do?


A.

Ask the client how the project will affect the client's organization and recommend that all impacted parties be involved.


B.

involve an executive-level stakeholder at the project manager's own company to speak with the client's executive sponsor.


C.

Perform an independent analysis to determine the stakeholders from the client's organization.


D.

Defer to the judgment of the client's executive sponsor since they will determine whether the project is a success.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.